Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Math question .. need help

Expert replies
by richlittl » Thu Oct 16, 2008 9:34 am
Two machines are sawing wood but due to space limitations only one at a time can operate. Machine A is used for the first shift and the other machine for the second shift, while both work half of the third shift. Machine A can do the job in 12 days if it worked two shifts and Machine B can do the job in 15 days if it worked two shifts. How many days will it take to do the job with current work schedule?

A.14

B.13

C.11

D.9

E.7

Isn't a "shift" a defined time frame??
Join the discussion
Source: — Problem Solving |

by mental » Thu Oct 16, 2008 10:29 am
Total 3 shifts worked per day, with each machine working for 1.5 shifts

Machine A:
2 shifts a day...................12 days to complete the work
1.5 shifts/day...................12*2/1.5 = 16 days to complete the work
in one day it does 1/16 of work

Machine B:
2 shifts a day...................15 days to complete the work
1.5 shifts/day...................15*2/1.5 = 20 days to complete the work
in one day it does 1/20 of work

working together they do 1/16 + 1/20 = 9/80 of work in a day
they complete the work in 80/9 = 9 approx

IMO: D
Join the discussion

by stop@800 » Thu Oct 16, 2008 10:01 pm
I am also getting 80/9
but I think there is no approximate in question so we must be missing something
Join the discussion

by mental » Thu Oct 16, 2008 11:54 pm
OA please
Join the discussion

by richlittl » Fri Oct 17, 2008 12:53 pm
D. 9 days