right wrong
Pick an answer to see how members did
Log this miss in the free GMAT error log
Get the error logGet one like this every day: the free 60-day plan
Start the plan(1) Machines X and Y, working together, fill a production order of this size in two-thirds the time that machine X, working alone, does
(2) Machine Y, working alone, fills a production order of this size in twice the time that machine X, working alone, does
[spoiler]OA=E[/spoiler]
Source: GMAT Prep