BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATBootcamp Starts Sep 28
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE BOOTCAMP

Live Online Bootcamp Class with Top GMAT Expert Chris Peckover

15 live classes from Sep 28, 2026

Schedule
Mon to Fri · 7:00 to 10:00 PM ET
Included
Live classes + 6 months of TTP OnDemand
  • Boost your GMAT score in less than one month in a live online class
  • 6 months access to TTP OnDemand video courses included
View bootcamp & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Machines-work problem

Expert replies
by hpgmat » Sat Oct 24, 2009 3:06 pm
six machines , each working at the same constant rate, together can complete a certain Job in 12 days. How many Additional machines, each working at the same constant rate will be needed to complete the Job in 8 days?

2
3
4
6
8

please show calc
Will Win
Join the discussion
Source: — Problem Solving |

Re: Machines-work problem

by Brent@GMATPrepNow » Sat Oct 24, 2009 3:27 pm
hpgmat wrote:six machines , each working at the same constant rate, together can complete a certain Job in 12 days. How many Additional machines, each working at the same constant rate will be needed to complete the Job in 8 days?
2
3
4
6
8
please show calc
If 6 machines take 12 days to complete the job, then we can say that the job takes 72 "machine days" to complete the job (6x12=72)

To complete the job in 8 days would require 9 machines (72 machine days divided by 8)

So, we need an additional 3 machines. B
Brent Hanneson - Creator of GMATPrepNow.com