BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

machines work problem (i never get these right)

Expert replies
by josh80 » Wed Dec 11, 2013 5:41 pm
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

2
3
4
6
8
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Wed Dec 11, 2013 5:49 pm
josh80 wrote:Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

A) 2
B) 3
C) 4
D) 6
E) 8
If 6 machines take 12 days to complete the job, then we can say that the job takes 72 "machine days" to complete the job (6x12=72)

To complete the job in 8 days would require 9 machines (72 machine days divided by 8 day = 9 machines)

So, we need an additional 3 machines.

Answer = B

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by Patrick_GMATFix » Wed Dec 11, 2013 10:26 pm
josh80 wrote:Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

2
3
4
6
8
Approach 1:
Since Work done = #_of_Machines * Rate * Time, we can say that the amount of work done by 6 machines over 12 days is 6 * r * 12 days = 72r.

If we have only 8 days to do the job, the equation becomes x * r * 8 = 72r where x is the number of machines. x=9 machines, so we need an extra 3 machines (on top of the original 6) to do the job in 8 days.

Approach 2:
If you notice that # of machines and time are inversely proportional (meaning that doubling the machines will cut the time in half), we can quickly solve.

the time goes from 12 days to 8 days, so time was multiplied by 2/3. As a result, # of machines will be multiplied by the inverse, 3/2. So the new # of machines will be 6 * 3/2 = 9 machines. We need an extra 3 machines.
  • Ask me about tutoring.
Join the discussion

by GMATGuruNY » Thu Dec 12, 2013 4:02 am
josh80 wrote:Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

2
3
4
6
8
Approach 1: Plug in a rate for EACH MACHINE

Let the rate for each machine = 1 unit per day.
Rate for 6 machines = 6 units per day.
In 12 days, the amount of work produced by 6 machines = r*t = 6*12 = 72 units.
To produce 72 units in 8 days, the required amount of work per day = w/t = 72/8 = 9 units per day.
To increase the rate from 6 units per day to 9 units per day, 3 more machines are needed.

The correct answer is B.

Approach 2: Inverse proportion method

The number of machines is INVERSELY PROPORTIONAL to the number of days:
(machines)(days) = (machines)(days).
As the number of machines INCREASES, the number of days must DECREASE, so that in each case the SAME AMOUNT OF WORK is produced.

Since 6 machines take 12 days, and the job is to be completed in 8 days, we get:
6 * 12 = m * 8
72 = 8m
m = 9.

Since 9 machines are required, the original number of machines -- 6 -- must increase by 3.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.