Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

machines R and S

Expert replies
by Xbond » Sat Dec 12, 2009 9:33 am
Hi

How resolve it ? OA is C

A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
Join the discussion
Source: — Problem Solving |

by Testluv » Sat Dec 12, 2009 9:58 am
Xbond wrote:Hi

How resolve it ? OA is C

A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
The combined time it takes two workers to do a job is the product of the individual times of the workers divided by the sum of the individual times:

Tab = Ta * Tb/(Ta + Tb)

Tab = 36*18/(36 + 18) = 36*18/54 = (6*6*9*2)/(6*9) = 6*2 = 12 hours.

So, if there was one R and one S, it would take them 12 hours to complete the job. We are told, however, that it took them only 2 hours to do the job (and that the number of them is equal). So, they actually did the job 12/2 = 6 times as fast as they would have had there been one machine of each type. So, there must be 6 machines of each type.
Kaplan Teacher in Toronto
Join the discussion

by heshamelaziry » Sat Dec 12, 2009 1:14 pm
This is exactly how I solved it too.
Join the discussion

by Stuart@KaplanGMAT » Sat Dec 12, 2009 1:53 pm
Xbond wrote:Hi

How resolve it ? OA is C

A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
Great solutions so far. This is a question on which common sense/backsolving also works great.

Before we backsolve, let's narrow down the choices with logic:

If we used all type S machines, it would take 18/2 = 9 total machines. Half of 9 is 4.5, so the answer must be more than 4.5: eliminate A and B.

If we used all type R machines, it would take 36/2 = 18 total machines. Half of 18 is 9, so the answer must be less than 9: eliminate D and E.

(I took half of each number because the question is asking only about one type of machine, and we're using the same number of each, so we want half of the total # of machines used.)

Well heck, only C is left, we don't even have to do any plugging in!
Image

Stuart Kovinsky | Kaplan GMAT Faculty | Toronto