Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Machines operating simultaneously

Expert replies
by alivapriyada » Tue Sep 14, 2010 12:51 pm
It takes machine A x hours to manufacture a deck of cards that machine B can manufacture in y hours. If machine A operates alone for z hours and is then joined by machine B until 100 decks are finished, for how long will the two machines operate simultaneously?


A. (100xy – z)/(x + y)

B. y(100x – z) /(x + y)

C. 100y(x – z)/(x + y)

D. x + y /(100xy – z)

E. (x + y – z)/ 100xy
Join the discussion
Source: — Problem Solving |

by goyalsau » Tue Sep 14, 2010 1:45 pm
alivapriyada wrote:It takes machine A x hours to manufacture a deck of cards that machine B can manufacture in y hours. If machine A operates alone for z hours and is then joined by machine B until 100 decks are finished, for how long will the two machines operate simultaneously?


A. (100xy – z)/(x + y)

B. y(100x – z) /(x + y)

C. 100y(x – z)/(x + y)

D. x + y /(100xy – z)

E. (x + y – z)/ 100xy

I will go with B.
what's the answer?
Join the discussion

by diebeatsthegmat » Tue Sep 14, 2010 7:52 pm
alivapriyada wrote:It takes machine A x hours to manufacture a deck of cards that machine B can manufacture in y hours. If machine A operates alone for z hours and is then joined by machine B until 100 decks are finished, for how long will the two machines operate simultaneously?


A. (100xy – z)/(x + y)

B. y(100x – z) /(x + y)

C. 100y(x – z)/(x + y)

D. x + y /(100xy – z)

E. (x + y – z)/ 100xy
A made 1 deck of card in x hour so in x hour it will make z/x deck of card
then B join with A.
the time it takes both A and B to make a deck of card is 1/x+1/y=1/a ( a is the time) so a= xy/x+y)
thus together they both have to make 100-z/x in b hour
b=(100-z/x)*xy/(x+y)
you calculated that and get the right answer B
Join the discussion

by alivapriyada » Tue Sep 14, 2010 11:16 pm
diebeatsthegmat wrote:
alivapriyada wrote:It takes machine A x hours to manufacture a deck of cards that machine B can manufacture in y hours. If machine A operates alone for z hours and is then joined by machine B until 100 decks are finished, for how long will the two machines operate simultaneously?


A. (100xy – z)/(x + y)

B. y(100x – z) /(x + y)

C. 100y(x – z)/(x + y)

D. x + y /(100xy – z)

E. (x + y – z)/ 100xy

A made 1 deck of card in x hour so in x hour it will make z/x deck of card
then B join with A.
the time it takes both A and B to make a deck of card is 1/x+1/y=1/a ( a is the time) so a= xy/x+y)
thus together they both have to make 100-z/x in b hour
b=(100-z/x)*xy/(x+y)
you calculated that and get the right answer B
many thanks!!! answer is B