Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

machine work!

Expert replies
by vscid » Tue Apr 06, 2010 6:28 pm
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?


* 14
* 13
* 11
* 9
* 7
The GMAT is indeed adaptable. Whenever I answer RC, it proficiently 'adapts' itself to mark my 'right' answer 'wrong'.
Join the discussion
Source: — Problem Solving |

by 4GMAT_Mumbai » Tue Apr 06, 2010 6:55 pm
IMO, the answer is 9 days.

The good part is that we do not have to do full calculations. We can figure out that the work gets done on the 9th day (without having to figure out as to how many hours into the day or as to how many shifts into the day)

A finishes the job in 24 shifts. B finishes in 30 shifts.

Part of the job done per day = (1/24 + 1/30 + 1/48 + 1/60).

Small suggestion - Do not take LCM of 24, 30, 48 and 60. Just add 1/24 and 1/48 first. Add 1/30 and 1/60 next. You are left with 1 / 16 + 1 / 20 = 9 / 80.

At the end of the 8th day, 72 / 80 parts of the job are done. At the end of the 9th day, 81 / 80 parts of the job are done - implying that the work gets done a few hours before the day ends. But, it does not matter as far as the question is concerned.

Hope this helps.
Join the discussion

by eaakbari » Tue Apr 06, 2010 8:35 pm
While doing 2 shifts A takes 12 days to complete,
therefore while doing 1 shift hell take 24
or doing 1.5 shifts(amount done in one day) he takes 16

Similarly B working everyday 1.5 shifts will take 20 days.

Now

1/20 + 1/16 = 1/x

x = 8.88 = 9 days