Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Machine M can produce x units in 3/4 of the time it takes...

Expert replies
by BTGmoderatorLU » Mon Mar 05, 2018 1:43 pm
Machine M can produce x units in 3/4 of the time it takes machine N to produce x units. Machine N can produce x units in 2/3 the time it takes machine O to produce x units. If all three machines are working simultaneously, what fraction of the total output is produced by machine N?

A. 1/2
B. 1/3
C. 4/13
D. 8/29
E. 6/33

The OA is B.

I'm confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Join the discussion
Source: — Problem Solving |

by mbawisdom » Mon Mar 05, 2018 1:51 pm
LUANDATO wrote:Machine M can produce x units in 3/4 of the time it takes machine N to produce x units. Machine N can produce x units in 2/3 the time it takes machine O to produce x units. If all three machines are working simultaneously, what fraction of the total output is produced by machine N?

A. 1/2
B. 1/3
C. 4/13
D. 8/29
E. 6/33

The OA is B.

I'm confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Let's start with Machine O since this one is the slowest. We can assign it a rate of R.
Machine N takes 2/3 of the time of Machine O so it has a rate that is 3/2 faster than Machine O--> rate is 1.5R
Machine M takes 3/4 of the time of Machine N so it has a rate that is 4/3 faster than Machine N --> rate is (4/3)(3/2)R = 2R

Together the machines have a rate of R + 1.5R + 2R = 4.5R
Rate of Machine N/Total Rate = 1.5R/4.5R = 1/3

Answer is B.
Join the discussion

by [email protected] » Mon Mar 05, 2018 2:17 pm
Hi LUANDATO,

We're told that Machine M can produce X units in 3/4 of the time it takes machine N to produce X units and Machine N can produce X units in 2/3 the time it takes machine O to produce X units. We're asked if all three machines are working simultaneously, what fraction of the total output is produced by machine N. This question can be solved by TESTing VALUES (but you need to focus on the amount of TIME each Machine takes and NOT the value of X).

IF... Machine O takes 12 hours to produce X units and....
Machine N takes (2/3)(12) = 8 hours to produce X units and....
Machine M takes (3/4)(8) = 6 hours to produce X units....

Let's have the Machines work for 24 hours...
Machine O will make (24/12)(X) = 2X units
Machine N will make (24/8)(X) = 3X units
Machine O will make (24/6)(X) = 4X units

2X + 3X + 4X = 9X total units produced. Machine N produces (3X)/(9X) = 1/3 of the units

Final Answer: B

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by swerve » Tue Mar 06, 2018 7:49 am
Hi LUANDATO,

Another way to look at the problem can be as follow,

Let the time taken be as

M = 12
N = 8
O = 6

Assume total work be 24 units.

Thus the efficiency of the three machines are asunder,

O = 2
N = 3
M = 4

Total efficiency is 9 (i.e 2 + 3 + 4)units/h

So, work done by N is 3/9 = 1/3. Option B.

Regards!
Join the discussion

by Jeff@TargetTestPrep » Thu Mar 08, 2018 4:38 pm
LUANDATO wrote:Machine M can produce x units in 3/4 of the time it takes machine N to produce x units. Machine N can produce x units in 2/3 the time it takes machine O to produce x units. If all three machines are working simultaneously, what fraction of the total output is produced by machine N?

A. 1/2
B. 1/3
C. 4/13
D. 8/29
E. 6/33
Let t = the time it takes machine O to produce x units; then the time it takes machine N to produce x units = (2/3)t, and the time it takes machine M to produce x units = (3/4)(2/3)t = (1/2)t.

Therefore, the rate of M is x/[(1/2)t] = 2x/t, the rate of N is x/[(2/3)t] = 3x/2t, and the rate of O is x/t. Their combined rate is 2x/t + 3x/2t + x/t = 4x/2t + 3x/2t + 2x/2t = 9x/2t.

If all three machines are working simultaneously, the fraction of the total output that is produced by machine N is:

(3x/2t)/(9x/2t) = 3x/9x = 1/3

Answer: B