BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Machine A takes 10 hours to complete a certain job and start

Expert replies
by ktrout2020 » Thu Oct 31, 2019 6:27 am
Machine A takes 10 hours to complete a certain job and starts that job at 9 am. After one hour of working alone, machine A is joined by machine B and together they complete the job at 5 pm. How long would it have taken machine B to complete the job if it had worked alone for the entire job?

(A) 15 hours
(B) 18 hours
(C) 20 hours
(D) 24 hours
(E) 35 hours

Source: Veritas
Answer: E
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Fri Nov 01, 2019 6:16 am
ktrout2020 wrote:Machine A takes 10 hours to complete a certain job and starts that job at 9 am. After one hour of working alone, machine A is joined by machine B and together they complete the job at 5 pm. How long would it have taken machine B to complete the job if it had worked alone for the entire job?

(A) 15 hours
(B) 18 hours
(C) 20 hours
(D) 24 hours
(E) 35 hours

Source: Veritas
Answer: E
One approach:

Working ALONE Machine A takes 10 hours to do the job.
With Machine B's help, the job took 8 hours to complete.
So, Machine B saved Machine A 2 hours of work.

In other words, during the 7 hours that Machine B was helping, Machine B did the work that would have taken Machine A an extra 2 hours to complete.
So, it takes Machine B 7 hours to complete the same amount of work that it takes Machine A to complete in 2 hours.
So, it takes Machine B 7/2 times as long to complete what Machine A can complete

It takes Machine A 10 hours to do the job.
So, the time it takes Machine B to do the job = (10)(7/2) = 35 = E

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by deloitte247 » Sat Nov 02, 2019 2:49 pm
Workdone by A in 1 hour = 1/10 hours
Work left for A and B after 1 hour = 1 - 1/10 = 9/10
Machine A could complete the whole work in 10 hours; it did 1/10 of the work in 1 hour.
Machine B joined Machine A after 1 hour.
With their combined effort, they completed 9/10 of the work in 7 hours.
Let the total time taken for machine B to complete the work = x hours
Machine B will complete 1/x of the jon in 1 hour
Total workdone by the 2 machines in 1 hour => (1/10) + (1/x) = (x+10)/10x
Workdone by the 2 machines in 7 hours to complete 9/10 of the work =>
$$\left(\frac{x+10}{10x}\cdot7\right)=\left(\frac{9}{10}\right)$$
Divide through by 7
$$\frac{x+10}{10x}=\frac{9}{10}\cdot\frac{1}{7}\ =\ \frac{9}{70}$$
By cross multiplying
70 (x + 10) = 9 (10x)
70x + 700 = 90x
20x = 700
x = 34
Therefore, it will take machine B 35 hours to finish the work alone. Hence, option E is the correct option.
Join the discussion

by Scott@TargetTestPrep » Sun Nov 03, 2019 7:31 pm
ktrout2020 wrote:Machine A takes 10 hours to complete a certain job and starts that job at 9 am. After one hour of working alone, machine A is joined by machine B and together they complete the job at 5 pm. How long would it have taken machine B to complete the job if it had worked alone for the entire job?

(A) 15 hours
(B) 18 hours
(C) 20 hours
(D) 24 hours
(E) 35 hours

Source: Veritas
Answer: E
We let n = the number of hours that it takes machine B to complete the job by itself. We know that machine A worked for 8 hours and machine B worked for 7 hours to complete the entire job. Thus, we can create the equation:

(1/10)(8) + (1/n)(7) = 1

8/10 + 7/n = 1

4/5 + 7/n = 1

7/n = 1/5

35 = n

Answer: E

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion