Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Machine A produces pencils at a constant rate of 9000

Expert replies
by AAPL » Tue Apr 09, 2019 6:25 am
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

GMAT Paper Tests

Machine A produces pencils at a constant rate of 9000 pencils per hour, and machine B produces pencils at a constant rate of 7000 pencils per hour. If the two machines together must produce 100,000 pencils and if each machine can operate for at most 8 hours, what is the least amount of time, in hours, that machine B must operate?

A. 4
B. 4 2/3
C. 5 1/3
D. 6
E. 6 1/4

OA A
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Tue Apr 09, 2019 6:57 am
AAPL wrote:GMAT Paper Tests

Machine A produces pencils at a constant rate of 9000 pencils per hour, and machine B produces pencils at a constant rate of 7000 pencils per hour. If the two machines together must produce 100,000 pencils and if each machine can operate for at most 8 hours, what is the least amount of time, in hours, that machine B must operate?

A. 4
B. 4 2/3
C. 5 1/3
D. 6
E. 6 1/4

OA A
To MINIMIZE machine B's operating time, we must MAXIMIZE the time machine A's operating time.
So, let machine A operate for the full 8 hours.
In 8 hours, machine A produces 72,000 pencils [8 hours x 9,000 pencils/hour =72,000 pencils]

So, the number of pencils machine B must make = 100,000 - 72,000 = 28,000

Time = output/rate
So, operating time = 28,000/7000 = 4 hours

Answer: A

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by Scott@TargetTestPrep » Wed Apr 10, 2019 4:49 pm
AAPL wrote:GMAT Paper Tests

Machine A produces pencils at a constant rate of 9000 pencils per hour, and machine B produces pencils at a constant rate of 7000 pencils per hour. If the two machines together must produce 100,000 pencils and if each machine can operate for at most 8 hours, what is the least amount of time, in hours, that machine B must operate?

A. 4
B. 4 2/3
C. 5 1/3
D. 6
E. 6 1/4

OA A
If machine B’s operational time is to be minimized, we must maximize the time for machine A to operate. Since each machine can operate for at most 8 hours, we can let machine A operate for the full 8 hours. Since the rate of machine A is 9000 pencils per hour, machine A produces 8 x 9000 = 72,000 pencils, and hence 28,000 pencils are left to be produced.

Thus, it will take machine B 28,000/7,000 = 4 hours to produce the remaining pencils.

Answer: A