Jeff was given a report to complete. In how many days can he complete the report, if his rate of completion is consistent?
1. Jeff can complete \(10\%\) of report in \(2\) days
2. After \(7\) days, there was still \(65\%\) of the report to be completed
OA D
1. Jeff can complete \(10\%\) of report in \(2\) days
2. After \(7\) days, there was still \(65\%\) of the report to be completed
OA D