Live GMAT classes with Target Test Prep start Nov 21 and Nov 24. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

It takes 6 technicians

Expert replies
by BTGmoderatorDC » Thu Jan 25, 2018 5:49 pm
It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11:00 AM, and one technician per hour is added beginning at 5:00 PM, at what time will the server be complete?

A. 7:30 PM
B. 7:45 PM
C. 8:00 PM
D. 9:00 AM
E. 10:00 PM

Can some experts show me how to solve it? Thank you

OA C
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Fri Jan 26, 2018 4:13 am
lheiannie07 wrote:It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11:00 AM, and one technician per hour is added beginning at 5:00 PM, at what time will the server be complete?

A. 7:30 PM
B. 7:45 PM
C. 8:00 PM
D. 9:00 AM
E. 10:00 PM
Let the rate for each technician = 1 unit per hour, implying that the rate for 6 technicians = 6 units per hour.
Since 6 technicians take 10 hours to produce a server, the total job = (rate for 6 technicians)(number of hours) = 6*10 = 60 units.

From 11am to 5pm -- a total of 6 hours -- the amount of work produced by 6 technicians = (rate for 6 technicians)(number of hours) = 6*6 = 36 units.
Remaining work = 60-36 = 24 units.

Starting at 5pm, one worker is added every hour, implying that the rate increases every hour by 1 unit.
Thus:
From 5-6pm, 7 units are produced.
Remaining work = 24-7 = 17 units.
From 6-7pm, 8 units are produced.
Remaining work = 17-8 = 9 units.
From 7-8pm, 9 units are produced.
Remaining work = 9-9 = 0 units.

Since no units remain, the server is finished by 8pm.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Jeff@TargetTestPrep » Mon Jan 29, 2018 10:19 am
lheiannie07 wrote:It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11:00 AM, and one technician per hour is added beginning at 5:00 PM, at what time will the server be complete?

A. 7:30 PM
B. 7:45 PM
C. 8:00 PM
D. 9:00 AM
E. 10:00 PM

We are given that six technicians can complete a job in 10 hours. Since rate = work/time, the rate of the 6 technicians is 1/10. Thus, the rate of 1 technician is (1/10)/6 = 1/60.

We see that 6 technicians work from 11:00 AM to 5:00 PM or 6 hours. Since rate x time = work, those technicians complete 1/10 x 6 = 6/10 = 3/5 of the job.

If another technician is added to the job at 5:00 PM, the new rate for the technicians is (1/60) x 7 = 7/60 and thus all 7 complete 7/60 of the job in that hour.

Thus, 3/5 + 7/60 = 36/60 + 7/60 = 43/60 of the job is complete

If another technician is added to the job at 6:00 PM, the new rate for the technicians is (1/60) x 8 = 8/60 and thus all 8 complete 8/60 of the job in that hour.

Thus, 43/60 + 8/60 = 51/60 of the job is complete

If another technician is added to the job at 7:00 PM, the new rate for the technicians is (1/60) x 9 = 9/60 and thus all 9 complete 9/60 of the job in that hour.

Thus, 51/60 + 9/60 = 60/60 of the job is complete at 8:00 PM.

Alternate Solution:

Since it takes 6 technicians a total of 10 hours to complete the server, we see that the entire job will require 60 labor-hours for completion.

For the 6 hours from 11 am to 5 pm, the 6 technicians will contribute 36 labor-hours to the task.

From 5 pm to 6 pm, the 7 technicians will contribute 7 more labor-hours, for a subtotal of 43 labor-hours.

From 6 pm to 7 pm, the 8 technicians will contribute 8 more labor-hours, for a subtotal of 51 labor-hours.

From 7 pm to 8 pm, the 9 technicians will contribute 9 more labor-hours, for a total of 60 labor-hours, thus completing the entire job at 8 p.m.

Answer: C