Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

It takes 6 beavers 10 hours to build a certain dam, working

Expert replies
by BTGmoderatorLU » Tue Dec 18, 2018 2:53 pm
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

Source: Princeton Review

It takes 6 beavers 10 hours to build a certain dam, working at a uniform rate. If six beavers start to build the same dam at noon, and one beaver per hour is added beginning at 6:00 PM, at what time will the dam be complete?

A. 7:40 PM
B. 8:00 PM
C. 8:20 PM
D. 8:40 PM
E. 9:00 PM

The OA is E
Join the discussion
Source: — Problem Solving |

by Jay@ManhattanReview » Tue Dec 18, 2018 9:56 pm
BTGmoderatorLU wrote:Source: Princeton Review

It takes 6 beavers 10 hours to build a certain dam, working at a uniform rate. If six beavers start to build the same dam at noon, and one beaver per hour is added beginning at 6:00 PM, at what time will the dam be complete?

A. 7:40 PM
B. 8:00 PM
C. 8:20 PM
D. 8:40 PM
E. 9:00 PM

The OA is E
Given, that it takes 6 beavers 10 hours to build a certain dam, we need 6*10 = 60 man-hours to complete the dam. Or, in 1 man-hour 1/60 dam is completed.

From 12 noon to 6 pm, in 6 hours, 6 beavers worked or contributed 6*6 = 36 man-hours. This way, 36/60 = 3/5 part of the dam is completed and 1 – 3/5 = 2.5 part of the dam is remaining to be completed.

Since by 6 pm, at every interval of one hour, one beaver is added, we have to compute at what time the dam is completed. Let's understand this at 7 pm, 8 pm, 9 pm, etc.

1. At 7 pm: From 6 to 7 pm, we have 7 weavers, thus 7*(1/60) = 7/60 part of the dam was completed. Thus, part of the dam remaining to be completed at 7 pm = 2/5 – 7/60 = 17/60 part

2. At 8 pm: From 7 to 8 pm, we have 8 weavers, thus 8*(1/60) = 2/15 part of the dam was completed. Thus, part of the dam remaining to be completed at 8 pm = 17/60 – 2/15 = 9/60 part

2. At 9 pm: From 8 to 9 pm, we have 9 weavers, thus 9*(1/60) part of the dam was completed. Thus, part of the dam remaining to be completed at 9 pm = 9/60 – 9/60 = 0. Dam is completed by 9 pm.

The correct answer: [spoilerE][/spoiler]

Hope this helps!

-Jay
_________________
Manhattan Review Test Prep

Locations: Manhattan Review Chennai | Free GMAT Practice Test | GRE Prep Hyderabad | Jayanagar GRE Coaching | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by Scott@TargetTestPrep » Sun Mar 03, 2019 6:31 pm
BTGmoderatorLU wrote:Source: Princeton Review

It takes 6 beavers 10 hours to build a certain dam, working at a uniform rate. If six beavers start to build the same dam at noon, and one beaver per hour is added beginning at 6:00 PM, at what time will the dam be complete?

A. 7:40 PM
B. 8:00 PM
C. 8:20 PM
D. 8:40 PM
E. 9:00 PM

The OA is E
If 6 beavers build a dam in 10 hours, the rate of 6 beavers is 1/10 of a dam per hour and the rate of 1 beaver is (1/10)/6 = 1/60 of a dam per hour.

If 6 beavers start to build a dam at noon, by 6 PM, they will complete 6 x (1/10) = 6/10 = 3/5 of the dam. So 1 - 3/5 = 2/5 of the dam remains to be completed at 6 PM.

At this time, a new beaver joins in; thus, the rate of the 7 beavers is 7 x (1/60) = 7/60 of a dam per hour, and they will complete 7/60 of the dam by 7 PM. So 2/5 - 7/60 = 24/60 - 7/60 = 17/60 of the dam remains to be completed at 7 PM.

At this time, another new beaver joins in; thus, the rate of the 8 beavers is 8 x (1/60) = 8/60 of a dam per hour and they will complete 8/60 of the dam by 8 PM. So 17/60 - 8/60 = 9/60 of thedam remains to be completed at 8 PM.

At this time, yet another new beaver joins in; thus, the rate of the 9 beavers is 9 x (1/60) = 9/60 of a dam per hour, and they will complete 9/60 of the dam by 9 PM. This completes the 9/60 of the dam that remained to be completed at 8 PM. Therefore, they complete the dam at 9 PM.

Alternate Solution:

If it takes 6 beavers 10 hours to build the dam, then a total of 60 beaver-hours is needed to complete the job. From noon to 6 p.m., we have 6 beavers working, so their total hours is 6 x 6 = 36 hours.

From 6 p.m to 7 p.m., 7 beavers work for 1 hour, so the total output since noon is 36 + 7 = 43 hours.

From 7 p.m. to 8 p.m., 8 beavers work for 1 hour, so the total output since noon is now 43 + 8 = 51 hours.

From 8 p.m. to 9 p.m., 9 beavers work for 1 hour, so the total output since noon is now 51 + 9 = 60 hours.

Thus, the dam is completed at 9 p.m.

Answer: E