BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

It takes 12 hours for Adam to paint a certain wall ; 8 hours for Ben to paint the same wall.

Expert replies
by Max@Math Revolution » Tue Sep 15, 2020 1:17 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

(Work rate) It takes 12 hours for Adam to paint a certain wall, and 8 hours for Ben to paint the same wall. Adam painted alone for 3 hours, and then Ben came to help Adam paint. After a while, Adam left, and Ben finished the job on his own in 1 hour. How many hours did Adam and Ben work together?

A. 1
B. 3
C. 5
D. 7
E. 9
Join the discussion
Source: — Problem Solving |

(Solution):

Adam takes 12 hours to paint a certain wall. In 1 hour, Adam will paint\(\frac{1}{12}\) of the wall.

Ben takes 8 hours to paint a certain wall. In 1 hour, Adam will paint \(\frac{1}{8}\) of the wall.

Adam started work and painted alone for 3 hours. Therefore, the amount of work done by Adam is:

=> \(\frac{1}{12}\) * 3 = \(\frac{1}{4}\) .


Adam and Ben together can finish (\(\frac{1}{12}\) + \(\frac{1}{8}\) = \(\frac{5}{24}\) ) work in 1 hour.

Ben painted for 1 hour alone at the end. Therefore, the amount of work done by Ben is:

=> 1 * \(\frac{1}{8}\) = \(\frac{1}{8}\).

Total work done:

=> \(\frac{1}{4}\) + \(\frac{1}{8}\) = \(\frac{3}{8}\).

Remaining work:

=> 1 - \(\frac{3}{8}\) = \(\frac{5}{8}\) of the work.

This work was done by Adam and Ben together:

=> \(\frac{5}{24}\) work in 1 hour = \(\frac{5}{8}\) the part of work to be completed in 3 hours since ( \(\frac{5}{24}\)) * 3 = \(\frac{5}{8}\).

Hence, Adam and Ben worked together for 3 hours.

Therefore, B is the correct answer

Answer B