BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

In 1990 the budgets for projects Q and V were $660,000 and

Expert replies
by BTGmoderatorLU » Wed Feb 27, 2019 2:42 pm

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

Source: GMAT Prep

In 1990 the budgets for projects Q and V were $660,000 and $780,000, respectively. In each of the next 10 years, the budget for Q was increased by $30,000 and the budget for V was decreased by $10,000. In which year was the budget for Q equal to the budget for V?

A. 1992
B. 1993
C. 1994
D. 1995
E. 1996

The OA is B
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Wed Feb 27, 2019 4:44 pm
BTGmoderatorLU wrote: Source: GMAT Prep

In 1990 the budgets for projects Q and V were $660,000 and $780,000, respectively. In each of the next 10 years, the budget for Q was increased by $30,000 and the budget for V was decreased by $10,000. In which year was the budget for Q equal to the budget for V?

A. 1992
B. 1993
C. 1994
D. 1995
E. 1996

The OA is B
One approach is to treat this is a rate question.

In 1990 the GAP BETWEEN V's budget and Q's budget was $120,000 ($780,000 - $660,000 = $120,000)

Each year, the budget for Q increased by $30,000 and the budget for V decreased by $10,000.
In other words, the GAP BETWEEN the budgets DECREASES by $40,000 each year

So, at a rate of $40,000 per year, it will take 3 years for the gap to decrease from $120,000 to $0

So, the gap will equal $0 (and the two budgets will be the same) in 1993

Answer: B

Cheers,
Brent