Start the planIf Max can complete a job in 4 hours and Nick can complete the same job in 6 hours, how many fewer hours do Max and Nick working together need to complete the job than Max alone needs to complete the job?
A. 1.6
B. 2.4
C. 3.2
D. 3.4
E. 5.0
The OA is A.