i falter in rate problems :( though being so easy

Expert replies
by divya23 » Wed Jun 01, 2011 9:55 pm
6 machines,each wrking at same constant rate,together can complete a job in 12 days.How many additional machines,each woeking at the same rate will be needed to comp job in 8 days?
A.2
B.3
C.4
D.6
E.8

[spoiler]OA = C[/spoiler]
Join the discussion
Source: — Problem Solving |

by cans » Wed Jun 01, 2011 10:24 pm
6 machines do work in 12 days
thus it means 1 machine alone can do work in 12*6 = 72 days
to complete work in 8 days, we need 72/8 = 9 machines
Thus additional of 9-6=3 machines.
IMO B
Join the discussion

by Frankenstein » Thu Jun 02, 2011 1:01 am
Hi,
B seems to be correct. Can you check OA again.
Cheers!

Things are not what they appear to be... nor are they otherwise
Join the discussion

by Ozlemg » Thu Jun 02, 2011 1:09 am
B seems the right answer.

12 days --->6 machines
8 days---> x machines
-------------------------

There is an indirect propotion btw the number of machines and the days.SO,
12*6)/ 8 = 9 machines

9-6 : 3 additional machines are required.
Join the discussion

by divya23 » Thu Jun 02, 2011 1:29 am
ya its 3 sorry ppl
Join the discussion

by galaxian » Thu Jun 02, 2011 9:58 am
A Good way to approach these problems is to Calculate Amount of work done in Man-Days (Machine days)
Like : 9 Man can do in 7 days => 9*7 Man Days of Work
or 6 Machines in 5 Hours => 6*5 Machine Hours of total work has to be done, this makes finding the unknown easier !
divya23 wrote:6 machines,each wrking at same constant rate,together can complete a job in 12 days.How many additional machines,each woeking at the same rate will be needed to comp job in 8 days?
A.2
B.3
C.4
D.6
E.8

[spoiler]OA = C[/spoiler]
Join the discussion