Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

I dont seem to get the calculation

Expert replies
by candygal79 » Fri Apr 04, 2014 12:25 am
In 1990 the budgets for projects Q & V were $660,000 and $ 780,000, respectively. In each of the next 10 years , the budget for Q increased by $ 30,000 and the budget for V decreased by $ 10,000. In which was the budget for Q equal to the budget for V ?

A 1992

B 1993

C 1994

D 1995

E 1996
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Fri Apr 04, 2014 3:00 am
In 1990 the budgets for projects Q and V were $660,000 and $780,000, respectively. In each of the next 10 years, the budget for Q was increased by $30,000 and the budget for V was decreased by $10,000. In which year was the budget for Q equal to the budget for V ?

(A) 1992
(B) 1993
(C) 1994
(D) 1995
(E) 1996
1990: Q = 660,000, V = 780,000

Each year, Q increases by 30,000, while V decreases by 10,000.
1991: Q = 690,000, V = 770,000
1992: Q = 720,000, V = 760,000
1993: Q = 750,000, V = 750,000.
The values are equal in 1993.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Abhishek009 » Fri Apr 04, 2014 6:39 am
candygal79 wrote:In 1990 the budgets for projects Q & V were $660,000 and $ 780,000, respectively. In each of the next 10 years , the budget for Q increased by $ 30,000 and the budget for V decreased by $ 10,000. In which was the budget for Q equal to the budget for V ?

A 1992

B 1993

C 1994

D 1995

E 1996
Frame and equation -

660,000 + 30,000 t = 780,000 - 10,000t

40,000t = 120,000

t = 3

hence the budget will be equall exactly after three years , so 1990 + 3 yrs = 1993
Abhishek
Join the discussion

by Brent@GMATPrepNow » Fri Apr 04, 2014 10:54 am
candygal79 wrote:In 1990 the budgets for projects Q & V were $660,000 and $ 780,000, respectively. In each of the next 10 years , the budget for Q increased by $ 30,000 and the budget for V decreased by $ 10,000. In which was the budget for Q equal to the budget for V ?

A 1992
B 1993
C 1994
D 1995
E 1996
We can treat this is a rate question.

In 1990 the GAP BETWEEN V's budget and Q's budget was $120,000 ($780,000 - $660,000 = $120,000)

Each year, the budget for Q increased by $30,000 and the budget for V decreased by $10,000. In other words, the GAP BETWEEN the budgets DECREASES by $40,000 each year

So, at a rate of $40,000 per year, it will take 3 years for the gap to decrease from $120,000 to $0

So, the gap will equal $0 (and the two budgets will be the same) in 1993

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com