BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Help With Work Problems

Expert replies
by and1ms238 » Sat Feb 20, 2010 12:33 pm
I was reviewing the BTG Flash cards and I came across this flash card. Can someone help explain to me the concept of 'inverting' here?

In the example, is A the amount of time?

For example: If machine A makes 5 gallons per Hour and machine B makes 8 gallons per hour, then how many can the two machines make together in 1 hour?

How does the formula in the flash card relate? Thank you much in advance.
Image
Join the discussion
Source: — Problem Solving |

by shashank.ism » Sat Feb 20, 2010 12:46 pm
and1ms238 wrote:I was reviewing the BTG Flash cards and I came across this flash card. Can someone help explain to me the concept of 'inverting' here?

In the example, is A the amount of time?

For example: If machine A makes 5 gallons per Hour and machine B makes 8 gallons per hour, then how many can the two machines make together in 1 hour?

How does the formula in the flash card relate? Thank you much in advance.
Image
see if a man do work in A hrs and other in B hrs say
so how much work he will do in 1 hr
a's work in 1 hr = 1/A
similarly B's work in 1 hr. = 1/B
total work in 1 hr = 1/A + 1/B

also if both can do work in T hr..
so their combined 1 hr work = 1/T

hence 1/A + 1/B =1/T/..
Hope it solves ur confusion....
My Websites:
www.mba.webmaggu.com - India's social Network for MBA Aspirants

www.deal.webmaggu.com -India's online discount, coupon, free stuff informer.

www.dictionary.webmaggu.com - A compact free online dictionary with images.

Nothing is Impossible, even Impossible says I'm possible.
Join the discussion

by ajith » Sat Feb 20, 2010 12:49 pm
and1ms238 wrote:I was reviewing the BTG Flash cards and I came across this flash card. Can someone help explain to me the concept of 'inverting' here?

In the example, is A the amount of time?

For example: If machine A makes 5 gallons per Hour and machine B makes 8 gallons per hour, then how many can the two machines make together in 1 hour?

How does the formula in the flash card relate? Thank you much in advance.
A is indeed the amount of time taken

In the example given , A makes 5 gallons per hour and B makes 8 gallons per hour; A&B together will make 13 gallons per hour.

If the question were A takes 2.6 Hours to make 13 gallons and B takes 1.625 Hours to make 13 gallons how much time will it take for A&B working together to make 13 gallons

In such scenario => 1/2.6+1/1.625 = 1/T

=> 1/1 = 1/T

T = 1 hour

I hope the concept is clear; A , B and T refer to time to get the specific amount of work done, not work done per time.
Always borrow money from a pessimist, he doesn't expect to be paid back.