Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Hard Work Problem

Expert replies
by rtaha2412 » Fri Nov 05, 2010 12:57 pm
Thanks for the help. I am stumped on this.

If 6 machines run at the same constant rate, they can complete a job in 8 hours. If only 5 of these machines run at this rate, how many more minutes will be required to complete the same job?

a 38
b 72
c 80
d 90
e 96
Join the discussion
Source: — Problem Solving |

by nadcreutz » Fri Nov 05, 2010 1:11 pm
Hey,

I believe the correct answer is c=80

It takes 6 machines 480min (8hrs*60min*6machines) to complete the job, which is 80 minutes per machine. Divide 480 by 5 machines, so it takes 5 machines 96 minutes per machine to complete the same job. That is 16 minutes per machine longer, so multiply this difference by 5 and you get 80 minutes.
Join the discussion

by goyalsau » Fri Nov 05, 2010 7:50 pm
nadcreutz wrote:Hey,

I believe the correct answer is c=80

It takes 6 machines 480min (8hrs*60min*6machines) to complete the job, which is 80 minutes per machine. Divide 480 by 5 machines, so it takes 5 machines 96 minutes per machine to complete the same job. That is 16 minutes per machine longer, so multiply this difference by 5 and you get 80 minutes.

I thought all the 6 machines are working for 8 hours simultaneously

I am getting the answer as 96

What is the OA?
Saurabh Goyal
[email protected]
-------------------------


EveryBody Wants to Win But Nobody wants to prepare for Win.
Join the discussion

by diebeatsthegmat » Sun Nov 07, 2010 12:28 pm
goyalsau wrote:
nadcreutz wrote:Hey,

I believe the correct answer is c=80

It takes 6 machines 480min (8hrs*60min*6machines) to complete the job, which is 80 minutes per machine. Divide 480 by 5 machines, so it takes 5 machines 96 minutes per machine to complete the same job. That is 16 minutes per machine longer, so multiply this difference by 5 and you get 80 minutes.

I thought all the 6 machines are working for 8 hours simultaneously

I am getting the answer as 96

What is the OA?
yeah you right, the answer must be 96...
6 machines work 480 minutes to finish the job ( at constant speed) so each machine works 80 minutes,
1 machine left thus only 5 machines work, they will have to do the job of the left machine thus 80/5=16
so each machine work more than 16 minutes ,,,,
Join the discussion

by GMATGuruNY » Mon Nov 08, 2010 4:17 am
rtaha2412 wrote:Thanks for the help. I am stumped on this.

If 6 machines run at the same constant rate, they can complete a job in 8 hours. If only 5 of these machines run at this rate, how many more minutes will be required to complete the same job?

a 38
b 72
c 80
d 90
e 96
An easy approach is to plug in a value for the work being completed by each machine.

Plug in that each machine completes 1 unit/hour.
Rate for 6 machines = 6*1 = 6 units/hour.
In 8 hours, r*t = 6*8 = 48 units are completed. This is the value of the job.
Rate for 5 machines = 5*1 = 5 units/hour.
Time for 5 machines = w/r = 48/5 = 9.6 hours
Additional time needed = 9.6 - 8 = 1.6 hours = 96 minutes.

The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by sbeagol1000 » Mon Mar 18, 2013 12:40 pm
I got E.

1 job/8 hours/6 machines = 1/48 or 48 hours

For 5 machines to do the same job requires 48hours/5machines = 9.6hrs

9.6hrs - 8 hrs = 1.6hrs

1.6hrs(60min) = 96 min
Join the discussion

by killerdrummer » Tue Mar 19, 2013 7:48 am
its E option 96 minutes

let us assume rate /day for each machine as r

Six machines for 8 days = 6r x 8 = 48r

now when same work i.e 48r has to be done with 5 machines it will be 48r/5r = 9.6 hours = (8 + 1.6) hours

1.6 hours equals 96 minutes.

I Hope it was clear!

---
KD
Join the discussion

by rairavig » Thu Mar 21, 2013 12:39 am
assume total work to be done = 8 units
done by 6 machines in 8 hours
each machine has contibutued in 8 hours = 8 units / 6
= 1.33 Units

5 machines will do in 8 hours 1.33 x 5 = 6.65 units .... (1)
total work is 8 units so teh work left to be done = 8 - 6.65 = 1.35 units .....(2)

from (1)..
1 hours efficiency of 5 machines = 6.65 / 8
= 0.831

number of hours taken to finish left 1.35 units work by 5 machines = 1.35 / 0.831
= 1.6 Hours = 96 Minutes