Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Engineer/Work Problem

Expert replies
by knight247 » Sat Jan 19, 2013 3:30 am
An engineer undertakes a project to build a road 15 KM long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 KM of the road has been completed. Find the number of extra men he must employ to finish the work in time.

(A)43
(B)46
(C)55
(D)68
(E)60

No OA. Detailed explanations would be appreciated. Thanks
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Sat Jan 19, 2013 4:32 am
knight247 wrote:An engineer undertakes a project to build a road 15 KM long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 KM of the road has been completed. Find the number of extra men he must employ to finish the work in time.

(A)43
(B)46
(C)55
(D)68
(E)60

No OA. Detailed explanations would be appreciated. Thanks
(men)(days) / work = (men)(days) / work.

Here is the reasoning behind the proportion above:
A certain number of MEN working for a certain number of DAYS (the numerator) are equivalent to a certain amount of WORK (the denominator)..

In 100 days, 45 men complete 2.5 kilometers.
The road is to be 15 kilometers and must be completed in 300 days total.
We need to determine how many men are needed to complete the remaining 12.5 kilometers in 200 days.
Thus:
(45)(100) / 2.5 = (x)(200) / 12.5
1800 = 16x
x = 112.5.

Since the number of men must be an integer value, the total number of men needed = 113.
Thus, the number of ADDITIONAL men needed = 113-45 = 68.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion