Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Dwight and Mose decide to build a new barn on their farm,

Expert replies
by BTGmoderatorDC » Sat Apr 13, 2019 9:22 pm
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512

OA D

Source: Veritas Prep
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Sun Apr 14, 2019 2:38 am
BTGmoderatorDC wrote:Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512
Every time Dwight does 1/4 of the remaining work, 3/4 of the work remains.
Every time Mose does 1/6 of the remaining work, 5/6 of the work remains.
When Mose starts his third shift, Dwight has completed 3 shifts, while Mose has completed 2 shifts.
Thus, the remaining work at the start of Mose's third shift = (3/4)(3/4)(3/4)(5/6)(5/6) = 75/256.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Scott@TargetTestPrep » Fri Apr 19, 2019 9:13 am
BTGmoderatorDC wrote:Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512

OA D

Source: Veritas Prep
The best way to solve this problem is to keep track of the fraction of the barn that still needs to be completed after each of their shifts:

Dwight’s 1st shift: 1/4 → Fraction of the barn still needs to be completed: 3/4

Mose’s 1st shift: 1/6(3/4) = 1/8 → Fraction of the barn still needs to be completed: 5/6(3/4) = 5/8

Dwight’s 2nd shift: 1/4(5/8) = 5/32 → Fraction of the barn still needs to be completed: 3/4(5/8) = 15/32

Mose’s 2nd shift: 1/6(15/32) = 5/64 → Fraction of the barn still needs to be completed: 5/6(15/32) = 25/64

Dwight’s 3rd shift: 1/4(25/64) = 25/256 → Fraction of the barn still needs to be completed: 3/4(25/64) = 75/256

We can see that before Mose begins his 3rd shift, 75/256 of the barn still needs to be completed.

Answer: D