Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Dwight and Mose decide to build a new barn on their farm, an

Expert replies
by BTGmoderatorDC » Mon Jan 28, 2019 11:04 pm
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512

OA D

Source: Veritas Prep
Join the discussion
Source: — Problem Solving |

by fskilnik@GMATH » Tue Jan 29, 2019 4:30 am
BTGmoderatorDC wrote:Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512
Source: Veritas Prep
$$?\,\,:\,\,{\rm{remaining}}\,\,\left( {{\rm{fraction}}} \right)\,\,{\rm{job}}\,\,{\rm{before}}\,\,{\rm{Mose}}\,\,{\rm{third}}\,\,{\rm{shift}}$$
Dwight 1st shift = (3/4) Job remaining.
Mose 1st shift = (5/6)*(3/4) Job remaining.

Dwight 2nd shift = (3/4)*(5/6)*(3/4) Job remaining.
Mose 2nd shift = (5/6)*(3/4)*(5/6)*(3/4) Job remaining.

Dwight 3rd shift = FOCUS = (3/4) *(5/6)*(3/4)*(5/6)*(3/4) Job remaining.
$${\rm{?}}\,\,{\rm{ = }}\,\,{3 \over 4} \cdot {5 \over 6} \cdot {3 \over 4} \cdot {5 \over 6} \cdot {3 \over 4}\,\, = \,\,{1 \over 4} \cdot {5 \over 2} \cdot {1 \over 4} \cdot {5 \over 2} \cdot {3 \over 4} = {{25 \cdot 3} \over {{4^4}}} = {{75} \over {256}}$$

We follow the notations and rationale taught in the GMATH method.

Regards,
Fabio.
Fabio Skilnik :: GMATH method creator ( Math for the GMAT)
English-speakers :: https://www.gmath.net
Portuguese-speakers :: https://www.gmath.com.br
Join the discussion

by Jay@ManhattanReview » Tue Jan 29, 2019 10:34 pm
BTGmoderatorDC wrote:Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512

OA D

Source: Veritas Prep
Since the question asks for the work left when Mose begins his third shift, Dwight must have done three and Mose must have done two shift.

Since we will have to deal with 1/4 three times and 1/6 two times, for the ease of calculation, let's assume that total work = (4^3)*(6^2) = 2304

1. Work done by Dwight in I shift = 1/4 of 2304 = 576;
2. Work left = [(4^3)*(6^2)] – 576 = 2304 – 576 = 1728;

3. Work done by Mose in I shift = 1/6 of 1728 = 288;
4. Work left = 1728 – 288 = 1440;

5. Work done by Dwight in II shift = 1/4 of 1440 = 360;
6. Work left = 1440 – 360 = 1080;

7. Work done by Mose in II shift = 1/6 of 1080 = 180;
8. Work left = 1080 – 180 = 900;

9. Work done by Dwight in III shift = 1/4 of 900 = 225;
10. Work left = 900 – 225 = 675

Part of work left to finish when Mose begins his third shift = 675/2304 = 225/768 = 75/256

The correct answer: D

Hope this helps!

-Jay
_________________
Manhattan Review GMAT Prep

Locations: GMAT Classes San Francisco | GMAT Tutoring Boston | GRE Prep Philadelphia | TOEFL Prep Classes DC | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by kyuhunl » Tue Jan 29, 2019 10:57 pm
BTGmoderatorDC wrote:Dwight and Mose decide to build a new barn on their farm, and they begin to work in alternating shifts, with Dwight taking the first shift. During each of his shifts, Dwight does 1/4 of the remaining work. During each of his shifts, Mose does 1/6 of the remaining work. How much of the barn is left to finish when Mose begins his third shift?

A. 1/24
B. 5/36
C. 25/72
D. 75/256
E. 255/512

OA D

Source: Veritas Prep
3/4 * 5/6 * 3/4 * 5/6 * 3/4 = 75/256