Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Drill Press M can bore 3000 holes an hour and Drill Press...

Expert replies
by BTGmoderatorLU » Fri Feb 09, 2018 7:24 am
Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?

A. 6
B. 7
C. 36/7
D. 8
E. 90/11

The OA is C.

I'm really confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Join the discussion
Source: — Problem Solving |

by EconomistGMATTutor » Fri Feb 09, 2018 8:02 am
LUANDATO wrote:Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?

A. 6
B. 7
C. 36/7
D. 8
E. 90/11

The OA is C.

I'm really confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Hello LUANDATO.

There is a mistake with the option C. The correct answer should be 36/5. Let's see why.

We know that Drill Press M has to operate for 9 hours (in this way, the number of hours that has to operate Drill Press N will be minimum). Hence, Drill Press M will bore 3000*9 = 27.000 holes.

Now, Drill Press N has to bore 45.000-27.000 = 18.000 holes.

The time that Drill Press N has to operate is 18.000 / 2.500 = 180 / 25 = 36/5 hours.

This is why the correct answer is 36/5 hours.

I hope this explanation may help you.

Feel free to ask me again if you have a doubt.

Regards.
GMAT Prep From The Economist
We offer 70+ point score improvement money back guarantee.
Our average student improves 98 points.

Image
Join the discussion

by Scott@TargetTestPrep » Mon Jul 01, 2019 4:19 pm
BTGmoderatorLU wrote:Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?

A. 6
B. 7
C. 36/7
D. 8
E. 90/11
We are given that the rate of Drill Press M is 3000 holes/hour and the rate of Drill Press N is 2500 holes/hour. Since each machine can operate for at most 9 hours and we need to determine the minimum number of hours of operating time for N, we can let M work for 9 hours, and thus 3000 x 9 = 27,000 holes are completed, leaving 45,000 - 27,000 = 18,000 holes to be completed by N.

Since time = work/rate, N must operate for 18,000/2,500 = 180/25 = 36/5 hours. (Note the typo for choice C, which should be 36/5.)

Answer: C