BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Drill Press M can bore 3000 holes an hour and Drill Press...

Expert replies
by BTGmoderatorLU » Fri Feb 09, 2018 7:24 am
Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?

A. 6
B. 7
C. 36/7
D. 8
E. 90/11

The OA is C.

I'm really confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Join the discussion
Source: — Problem Solving |

by EconomistGMATTutor » Fri Feb 09, 2018 8:02 am
LUANDATO wrote:Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?

A. 6
B. 7
C. 36/7
D. 8
E. 90/11

The OA is C.

I'm really confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Hello LUANDATO.

There is a mistake with the option C. The correct answer should be 36/5. Let's see why.

We know that Drill Press M has to operate for 9 hours (in this way, the number of hours that has to operate Drill Press N will be minimum). Hence, Drill Press M will bore 3000*9 = 27.000 holes.

Now, Drill Press N has to bore 45.000-27.000 = 18.000 holes.

The time that Drill Press N has to operate is 18.000 / 2.500 = 180 / 25 = 36/5 hours.

This is why the correct answer is 36/5 hours.

I hope this explanation may help you.

Feel free to ask me again if you have a doubt.

Regards.
GMAT Prep From The Economist
We offer 70+ point score improvement money back guarantee.
Our average student improves 98 points.

Image
Join the discussion

by Scott@TargetTestPrep » Mon Jul 01, 2019 4:19 pm
BTGmoderatorLU wrote:Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?

A. 6
B. 7
C. 36/7
D. 8
E. 90/11
We are given that the rate of Drill Press M is 3000 holes/hour and the rate of Drill Press N is 2500 holes/hour. Since each machine can operate for at most 9 hours and we need to determine the minimum number of hours of operating time for N, we can let M work for 9 hours, and thus 3000 x 9 = 27,000 holes are completed, leaving 45,000 - 27,000 = 18,000 holes to be completed by N.

Since time = work/rate, N must operate for 18,000/2,500 = 180/25 = 36/5 hours. (Note the typo for choice C, which should be 36/5.)

Answer: C