Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

cistern and pipe

Expert replies
by hemant_rajput » Mon Jan 28, 2013 8:54 am
Q28 . A tank of 425 liters capacity has been filled with water through two pipes, the first pipe having been opened 5 hours longer than the second. If the first pipe were open as long as the second pipe, the first pipe deliver half the amount of water delivered by second pipe; if the two pipes were open simultaneously, the tank would be filled up in 17 hours. How long was the second pipe open?
a. 10
b. 12
c. 15
d. 18
Last edited by hemant_rajput on Mon Jan 28, 2013 9:25 pm, edited 1 time in total.
I'm no expert, just trying to work on my skills. If I've made any mistakes please bear with me.
Join the discussion
Source: — Problem Solving |

by tisrar02 » Mon Jan 28, 2013 12:35 pm
IMO:C

OA and Source??

I think your also missing an answer choice (E)
Dedication is what leads to success...
Join the discussion

by guerrero » Mon Jan 28, 2013 1:19 pm
I got an approximate ans as 15 .. It involves a very tedious calculation . Doesn't look like a typical GMAT Q .

Anyway , let me know the OA and I will post the solution .

thanks !
Join the discussion

by GMATGuruNY » Mon Jan 28, 2013 3:45 pm
Some crucial information seems to be missing.
I believe that the following reflects the problem's intent:
Yesterday, Al and Bill produced a lot of 425 widgets. Al worked for x+5 hours and Bill worked for x hours. In x hours, Al can produce half as many widgets as Bill can produce in x+5 hours. Working together, Al and Bill can produce the entire lot in 17 hours. What is the value of x?

a)10 hrs
b)12 hrs
c)15 hrs
d)18 hrs
Since Al and Bill can produce the entire lot in 17 hours, the combined rate for Al and Bill = w/t = 425/17 = 25 widgets per hour.

We can plug in the answers, which represent the value of x.
Given that the lot = 425, the combined rate = 25, and the difference between x and x+5 is 5, the correct answer is almost certainly a multiple of 5.

Answer choice C: Bill worked for x=15 hours, implying that Al worked for x+5 = 15+5 = 20 hours
In 15 hours, the number of widgets produced by Al and Bill working together = r*t = 25*15 = 375.
Remaining work = 425-375 = 50 widgets.

These 50 widgets must have been produced by Al during the 5 hours that he worked alone.
Thus, Al's rate = w/t = 50/5 = 10 widgets per hour.
Thus, Bill's rate = (combined rate for Al and Bill) - (Al's rate alone) = 25-10 = 15 widgets per hour.

In x=15 hours, the number of widgets produced by Al = r*t = 10*15 = 150 widgets.
In x+5=20 hours, the number of widgets produced by Bill = r*t = 15*20 = 300 widgets.
Success!
In x hours, Al produces half the number of widgets that Bill produces in x+5 hours.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by hemant_rajput » Mon Jan 28, 2013 9:24 pm
GMATGuruNY wrote:Some crucial information seems to be missing.
I believe that the following reflects the problem's intent:
Yesterday, Al and Bill produced a lot of 425 widgets. Al worked for x+5 hours and Bill worked for x hours. In x hours, Al can produce half as many widgets as Bill can produce in x+5 hours. Working together, Al and Bill can produce the entire lot in 17 hours. What is the value of x?

a)10 hrs
b)12 hrs
c)15 hrs
d)18 hrs
Since Al and Bill can produce the entire lot in 17 hours, the combined rate for Al and Bill = w/t = 425/17 = 25 widgets per hour.

We can plug in the answers, which represent the value of x.
Given that the lot = 425, the combined rate = 25, and the difference between x and x+5 is 5, the correct answer is almost certainly a multiple of 5.

Answer choice C: Bill worked for x=15 hours, implying that Al worked for x+5 = 15+5 = 20 hours
In 15 hours, the number of widgets produced by Al and Bill working together = r*t = 25*15 = 375.
Remaining work = 425-375 = 50 widgets.

These 50 widgets must have been produced by Al during the 5 hours that he worked alone.
Thus, Al's rate = w/t = 50/5 = 10 widgets per hour.
Thus, Bill's rate = (combined rate for Al and Bill) - (Al's rate alone) = 25-10 = 15 widgets per hour.

In x=15 hours, the number of widgets produced by Al = r*t = 10*15 = 150 widgets.
In x+5=20 hours, the number of widgets produced by Bill = r*t = 15*20 = 300 widgets.
Success!
In x hours, Al produces half the number of widgets that Bill produces in x+5 hours.

The correct answer is C.

Sorry guys, I missed the part during typing.

Anyways Guru has provided the complete question. Also I've modified the original post for anyone's future reference.
I'm no expert, just trying to work on my skills. If I've made any mistakes please bear with me.
Join the discussion

by hemant_rajput » Tue Jan 29, 2013 8:06 am
guerrero wrote:I got an approximate ans as 15 .. It involves a very tedious calculation . Doesn't look like a typical GMAT Q .

Anyway , let me know the OA and I will post the solution .

thanks !
please stop giving such lame excuses. Just because you method takes time it doesn't mean other method don't exist.
I'm no expert, just trying to work on my skills. If I've made any mistakes please bear with me.