BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

(C) 2008 GMAT Club - [t]m07#6[/t]

Expert replies
by logitech » Fri Jan 16, 2009 12:33 am
Please time yourself when you practice :

A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?



* 4
* 5
* 6
* 7
* 8
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion
Source: — Problem Solving |

by 4meonly » Fri Jan 16, 2009 1:28 am
A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?
Hope I wil not get such Q in my test

Work=Rate*Time

A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain.
Means that the rate of 1 worker is 1/1100
We have 10 woker, so the group rate is 10/1100 = 1/110


However, after 5 days of rain, on the 61-st day,
Crew worked 55 days and made 55/110 = 1/2 of all work
Remaining part is 1/2

on the 61-st day, he hired 6 more people to finish the project early
Now rate is 16/1100

If the job was done in 100 days,
Group had 40 days to work, among these 40 days X days was rain. So, they really worked (40-x) days

((40-x)16)/1100 = 1/2
Solving we get x=5.625.
Here I was confused: 5.625 is not an integer :-(
But I will choose 5 days for rain because:

Substituting x=6 to ((40-x)16)/1100 = 544/1100 this is less than 1/2
Substituting x=5 to ((40-x)16)/1100 = 560/1100 this is more than 1/2

if the rain was on 6 days group finished on the 101 day
if the rain was on 5 days group finished on the 100 day (e.g. in afternoon)

So, 5 days is better.

B
Last edited by 4meonly on Fri Jan 16, 2009 12:42 pm, edited 2 times in total.
Join the discussion

by logitech » Fri Jan 16, 2009 1:48 am
Text book explanation!
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

by 4meonly » Fri Jan 16, 2009 2:23 am
This is a compliment? :)
Join the discussion

by logitech » Fri Jan 16, 2009 2:36 am
4meonly wrote:This is a compliment? :)
Yes it is master. Beautiful solution. Thank you.
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

by Mr2Bits » Fri Jan 16, 2009 9:29 am
I took a little different approach which may be quicker.

I first figured out how much work each man does each day.

10 workers each day 110 days of work, each worker does .10 of the work each day.

.10 *10 *55 days of work (60-5 rain days = 55 days)

So from this point half of the work is done. Well the boss adds 6 more dudes making each day work complete 1.6 labor days per day

55 days of work left / 1.6 labor days = 34.5 aprox 35 days of work to complete the job. Well since they completed this job in 100 days, 100-60 = 40 - 35 when they actually worked is 5 days they took off for the rain.

Whew :oops: