Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

(C) 2008 GMAT Club - [t]m07#6[/t]

Expert replies
by logitech » Fri Jan 16, 2009 12:33 am
Please time yourself when you practice :

A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?



* 4
* 5
* 6
* 7
* 8
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion
Source: — Problem Solving |

by 4meonly » Fri Jan 16, 2009 1:28 am
A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?
Hope I wil not get such Q in my test

Work=Rate*Time

A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain.
Means that the rate of 1 worker is 1/1100
We have 10 woker, so the group rate is 10/1100 = 1/110


However, after 5 days of rain, on the 61-st day,
Crew worked 55 days and made 55/110 = 1/2 of all work
Remaining part is 1/2

on the 61-st day, he hired 6 more people to finish the project early
Now rate is 16/1100

If the job was done in 100 days,
Group had 40 days to work, among these 40 days X days was rain. So, they really worked (40-x) days

((40-x)16)/1100 = 1/2
Solving we get x=5.625.
Here I was confused: 5.625 is not an integer :-(
But I will choose 5 days for rain because:

Substituting x=6 to ((40-x)16)/1100 = 544/1100 this is less than 1/2
Substituting x=5 to ((40-x)16)/1100 = 560/1100 this is more than 1/2

if the rain was on 6 days group finished on the 101 day
if the rain was on 5 days group finished on the 100 day (e.g. in afternoon)

So, 5 days is better.

B
Last edited by 4meonly on Fri Jan 16, 2009 12:42 pm, edited 2 times in total.
Join the discussion

by logitech » Fri Jan 16, 2009 1:48 am
Text book explanation!
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

by 4meonly » Fri Jan 16, 2009 2:23 am
This is a compliment? :)
Join the discussion

by logitech » Fri Jan 16, 2009 2:36 am
4meonly wrote:This is a compliment? :)
Yes it is master. Beautiful solution. Thank you.
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

by Mr2Bits » Fri Jan 16, 2009 9:29 am
I took a little different approach which may be quicker.

I first figured out how much work each man does each day.

10 workers each day 110 days of work, each worker does .10 of the work each day.

.10 *10 *55 days of work (60-5 rain days = 55 days)

So from this point half of the work is done. Well the boss adds 6 more dudes making each day work complete 1.6 labor days per day

55 days of work left / 1.6 labor days = 34.5 aprox 35 days of work to complete the job. Well since they completed this job in 100 days, 100-60 = 40 - 35 when they actually worked is 5 days they took off for the rain.

Whew :oops: