Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

At an auto detailing company, it takes 15 minutes for an

Expert replies
by swerve » Mon Nov 26, 2018 10:21 am
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

At an auto detailing company, it takes 15 minutes for an employee to service a car and 24 minutes to service a truck. If the company needs to service all 300 trucks and 360 cars on a lot during a six-hour shift, how many employees will it need to complete the job?

A. 35
B. 36
C. 40
D. 42
E. 45

The OA is A.

Source: Veritas Prep
Join the discussion
Source: — Problem Solving |

by rrnicky » Mon Nov 26, 2018 11:17 am
car servicing rate = 1/15 car per minute per employee
truck servicing rate = 1/24 truck per minute per employee
lets say n employees for car servicing and m employees for truck servicing are needed
then
cars repaired in 6 hrs (=6 x 60 min) by n employees = n x 6 x 60 x 1/15 = 360
truck repaired in 6 hrs (=6 x 60 min) by m employees = m x 6 x 60 x 1/24 = 300
solving both equations gives
n = 15, m = 20
total employees needed = 15+20 = 35

hence A is correct
Join the discussion

by [email protected] » Mon Nov 26, 2018 7:18 pm
Hi All,

We're told that at an auto detailing company, it takes 15 minutes for an employee to service a car and 24 minutes to service a truck and the company needs to service all 300 trucks and 360 cars on a lot during a 6-hour shift. We're asked for the number of employees needed to complete the job. This question can be approached in a number of different ways (depending on how you choose to organize the information).

Each car takes 15 minutes to service = 1/4 of an hour to service. With 360 cars, we would need (1/4)(360) = 360/4 = 90 hours of service to be done
Each truck takes 24 minutes to service = 2/5 of an hour to service. With 300 cars, we would need (2/5)(300) = 600/5 = 120 hours of service to be done
Total service time needed would be 90 + 120 = 210 hours of service

Since each employee is working for 6 hours, we would need 210/6 = 35 employees to complete the work in 6 hours.

Final Answer: A

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

swerve wrote:At an auto detailing company, it takes 15 minutes for an employee to service a car and 24 minutes to service a truck. If the company needs to service all 300 trucks and 360 cars on a lot during a six-hour shift, how many employees will it need to complete the job?

A. 35
B. 36
C. 40
D. 42
E. 45
Source: Veritas Prep
\[?\,\,\,\, = \,\,\,\,N\,\,\left( {{\text{for}}\,\,{\text{cars}}} \right)\,\,\, + \,\,\,M\,\,\left( {{\text{for}}\,\,{\text{trucks}}} \right)\]
Excellent opportunity for UNITS CONTROL, one of the most powerful tools of our method!

\[6\,{\text{h}}\,\,\,\left( {\frac{{60\,\min }}{{1\,{\text{h}}}}} \right)\,\, \cdot \,\,N\,{\text{employees}}\,\,\,\left( {\frac{{{\text{1}}\,{\text{car}}}}{{15\,\min \,\,\, \cdot \,\,\,1\,{\text{employee}}}}} \right)\,\,\,\, = \,\,\,\,360\,\,{\text{cars}}\,\,\,\,\, \Rightarrow \,\,\,\,\,N = 15\]
\[6\,{\text{h}}\,\,\,\left( {\frac{{60\,\min }}{{1\,{\text{h}}}}} \right)\,\, \cdot \,\,M\,{\text{employees}}\,\,\,\left( {\frac{{{\text{1}}\,{\text{truck}}}}{{24\,\min \,\,\, \cdot \,\,\,1\,{\text{employee}}}}} \right)\,\,\,\, = \,\,\,\,300\,\,{\text{trucks}}\,\,\,\,\, \Rightarrow \,\,\,\,\,M = 20\]
\[? = 15 + 20 = 35\]

This solution follows the notations and rationale taught in the GMATH method.

Regards,
Fabio.