Decoding everything, worker B makes a lamp in 16 hours, and worker A makes a lamp in somewhere between 8 and 12 hours. We'll find the minimum time it might take them together if we assume A takes exactly 8 hours. In that case, using any rates method you like (e.g. if A makes one lamp in 8 hours, A makes 2 lamps in 16 hours, so together A+B will make 3 lamps in 16 hours, or one lamp every 16/3 hours = 5h20m), we find it takes them at least 5h20m. So accounting for their one hour lunch break, they must finish the lamp after 2:20pm on Thursday, working together. Now we could also find the maximum time they could need together, but that's unnecessary. There can only be one right answer to a GMAT question, so whatever maximum we find, it will need to make one answer choice possible and the rest impossible. So whatever that maximum is, it will need to make 3:00pm Thursday possible, but any later choice impossible, and only C can be correct.
For online GMAT math tutoring, or to buy my higher-level Quant books and problem sets, contact me at ianstewartgmat at gmail.com
ianstewartgmat.com