An assembly line produces 40 cogs per hour until an initial order of 60 cogs is completed. The speed of the assembly

Expert replies
by VJesus12 » Wed Dec 16, 2020 4:35 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

An assembly line produces 40 cogs per hour until an initial order of 60 cogs is completed. The speed of the assembly line is then immediately increased so that it can produce 60 cogs per hour until another 60 cogs are produced. What is the average output, in cogs per hour, for the assembly line during this time?

A) 42
B) 45
C) 48
D) 50
E) 55

Answer: C