Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Allan and Bob complete the task

Expert replies
by bhumika.k.shah » Sun Jan 24, 2010 6:06 am
Allan can complete the task in 8 hours. Bob can complete the task in 12 hours. If Allan works on the task alone for 4 hours and then Bob starts to help him, how many hours in total will Allan have worked by the time the task is finished?

A.5
B.5.2
C.5.6
D.6.4
E.7.2

OA D

i dint quite understand what is really needed :-(
Join the discussion
Source: — Problem Solving |

by rahul.s » Sun Jan 24, 2010 6:23 am
let's assume the task is to place bricks and 24 (common to both, 8 and 24) bricks need to be placed.

so alan takes 8 hours to place 24 bricks
in one hour, he places 3 bricks (cross multiplication)

now bob takes 12 hours to place 24 bricks
so in 1 hour, he places 2 bricks.

alan works for 4 hours. 3*4 = 12 bricks
now bob joins him. so from now on, together they place 3 + 2 = 5 bricks in one hour

12 are placed, 12 more to go. 12/5 = 2.4 hours.

so the first 4 hours + 2.4 hours = 6.4 hours. hence, D
Join the discussion

by bhumika.k.shah » Sun Jan 24, 2010 6:28 am
But the question asks for how many hours will Allan have worked by the time the task is finished.
So why are we adding the time spent by Bob also ?
Last edited by bhumika.k.shah on Sun Jan 24, 2010 7:08 am, edited 1 time in total.
Join the discussion

by rahul.s » Sun Jan 24, 2010 7:07 am
bhumika.k.shah wrote:Allan can complete the task in 8 hours. Bob can complete the task in 12 hours. If Allan works on the task alone for 4 hours and then Bob starts to help him, how many hours in total will Allan have worked by the time the task is finished?

A.5
B.5.2
C.5.6
D.6.4
E.7.2

OA D

i dint quite understand what is really needed :-(
the question posted by you asks about Alan, not Bob.
Join the discussion

by Stuart@KaplanGMAT » Sun Jan 24, 2010 7:18 am
bhumika.k.shah wrote:Allan can complete the task in 8 hours. Bob can complete the task in 12 hours. If Allan works on the task alone for 4 hours and then Bob starts to help him, how many hours in total will Allan have worked by the time the task is finished?

A.5
B.5.2
C.5.6
D.6.4
E.7.2
Picking numbers is one great approach - we can also solve using the work formula, as long as we're careful.

If it takes Allan 8 hours to do a full job, then in 4 hours he'll have completed exactly 1/2 the task.

To complete 1/2 the job, it takes Allan 4 hours and Bob 6 hours (1/2 of the 12 hours it takes to do the full job). Now we can use the simple work formula:

Combined time (2 workers) = A*B/(A+B)

in which A and B are the times it takes them to do the job alone.

So:

CT (Allan and Bob) = 4*6/4+6 = 24/10 = 2.4 hours.

So, Allan worked 4 hours alone and then 2.4 hours in conjunction with Bob for a total of 6.4 hours: choose (D).
Image

Stuart Kovinsky | Kaplan GMAT Faculty | Toronto