Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Advanced

Expert replies
by pbanavara » Thu Jan 08, 2009 8:41 pm
This is from the website that Brent had mentioned.

If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars?

A. 5/3
B. 9/4
C. 8/3
D. 11/4
E. 10/3
In the land of night, the chariot of the sun is drawn by the grateful dead
https://questor.blocked

GMATPREP1 - 550 (Oct 08)
MGMAT FREE CAT - 600 (Dec 08)
MGMAT CAT1 - 670 (Jan 09)
MGMAT CAT2 - 550 (Jan 09)
MGMAT CAT3 - 640 ( Feb 09)
MGMAT CAT4 - 660 ( Feb 09)
Join the discussion
Source: — Problem Solving |

Re: Advanced

by vivek.kapoor83 » Thu Jan 08, 2009 8:49 pm
pbanavara wrote:This is from the website that Brent had mentioned.

If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars?

A. 5/3
B. 9/4
C. 8/3
D. 11/4
E. 10/3

4 cars in 2 days
means 2 cars in 1 day.
Suppose 1 car req 3 unit of work and that means 6 unit of work is produced by 6 workers in 1 day

So, 8 workers will produce 8 Units of work in 1 day
total work - 6cars*(3unit/car,as assumed) = 18 unit

8 units in 1 day
1 unit in 1/8 day
18 unit in 18/8 days
= 9/4 days
Hence B
Join the discussion

Re: Advanced

by logitech » Thu Jan 08, 2009 8:52 pm
6 workers, if they build 4 cars in 2 days, they can build 6 cars in 3 days.

if 6 workers 3 days, how about 8 workers same number of cars ?

3x6/8 = 9/4
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

by cramya » Thu Jan 08, 2009 9:25 pm
We all cant be Logitech and do it one line(Wow) :P so for the less gifted like me :wink: here's a solution/explanation

Calculate the rate for 1 worker from 6 workers can build 4 cars in 2 days

6 workers 2 cars 1 day

1 worker rate 1/3 CAR 1 DAY

8 workers rate 8/3

8/3 cars 1day
6cars ?

1/8/3*6 = 3/8*6 = 9/4


Regards,
CR
Join the discussion

by pbanavara » Thu Jan 08, 2009 9:30 pm
Thanks guys. Every solution posted is very helpful.

- pradeep
In the land of night, the chariot of the sun is drawn by the grateful dead
https://questor.blocked

GMATPREP1 - 550 (Oct 08)
MGMAT FREE CAT - 600 (Dec 08)
MGMAT CAT1 - 670 (Jan 09)
MGMAT CAT2 - 550 (Jan 09)
MGMAT CAT3 - 640 ( Feb 09)
MGMAT CAT4 - 660 ( Feb 09)
Join the discussion

by cramya » Thu Jan 08, 2009 9:33 pm
No probs Pradeep! We r all here to learn and help..

Good luck on your GMAT journey!!
Join the discussion

by ronniecoleman » Thu Jan 08, 2009 10:44 pm
let R be the rate of work

so

6* r* 2 = 4

let x days it takes

8* r* x = 6

solve 1 and 2 to get x