At first you have said to calculate 12 days is baseless. However, again you have used 12 days to find out 8 days. Can you please explain?
Cheers.
Anurag@Gurome wrote:You're assuming that A and B together has completed the job in 12 days and then you are saying A has left after 2 days! That makes your initial assumption (i.e. A and B together has completed the job in 12 days) baseless! And thus A did not left after 2 days.eyelikecheese wrote:Hey guys I'm arriving at a different answer. Can someone explain this to me.
1/20 +1/30 is 1/12 of the job/each day
So it takes 12 days to complete the job. Thus, 2 days into it, A quits.
1/6 of the job has been done in 2 days and B has 1/30 of the job for the remaining 5/6 of the job. This comes to 25 days+the original 2=27?
What am I computing wrong?
After how many days A left the work depends upon the total number of days it took to complete the job. Thus it's a reverse calculation problem.
A left 10 days before the project is complete.
Thus for last 10 days only B has done the work => In last 10 days B has done (10/30) = 1/3 of the project.
Thus, A and B together has done 2/3 of the project.
To do 2/3 of the project A and B together took 12*(2/3) = 8 days
Thus the number of days the project took to be completed = Number of days together A and B worked + number of days only B worked = 8 + 10 = 18
The correct answer is A.












