BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
Vote for Target Test Prep, Newsweek Readers’ Choice Awards 2026
NEWSWEEK READERS’ CHOICE 2026

BIG NEWS! Target Test Prep has been nominated, and they’d love your vote!

TTP has worked incredibly hard to build the best test prep experience possible, and winning Newsweek’s 2026 Readers’ Choice Award for Best Test Prep would mean a lot to them. If TTP has helped you, they’d be incredibly grateful for your vote. You can vote once each day through September 9.

Vote for TTP
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

A quits before the project is completed

Expert replies

by nisagl750 » Sun Mar 25, 2012 6:40 am
If A quits 10 days before the job is completed, then B alone take 10 days to complete the remaining job.

B's 1 day's work = 1/30

So, B's 10 Days days' work = 10/30 = 1/3

That means, 2/3 of work was completed by A & B Together.

A&B together take = (20x30)/(20+30) Days to complete the full work = 12 Days

To complete 1 unit work A & B take 12 days...

So to complete 2/3 unit of work

A&B would take (2/3)x12 = 8 Days.

Total time to complete the work = (Time take by A&B together + 10 days) = 8+10

18 Days

Option A :)
Join the discussion

by Lifetron » Mon Jul 30, 2012 4:25 am
(x-10)/20 + x/30 = 1

3x-30+2x=60

5x=90

x=18
Join the discussion

by chris558 » Sun Aug 26, 2012 7:19 am
Rate * Time = Distance
Let's first start by picking a number that represents 1 complete job. It would be easier if it were the LCD of 20 and 30... Let's say, 60.
So 1 job = 60

A: Rate * 20 = 60
Rate=3
B: Rate * 30 = 60
Rate = 2

They both work together to complete a job except B works the last 10 days by himself. The rate at which they both work together is 3 + 2.
Let t represent time (in days). Therefore the equation is:

5(t-10)+3(10)=60
5t-50+30=60
5t=80
t=18

Answer is A
Join the discussion

by r_vgupta » Thu Aug 30, 2012 12:27 am
TOGETHER THEY CAN DO WORK IN 12 DAYS.
A LEFT 10 DAYS BEFORE.ie B WORKED ALONE FOR 10 DAYS.
IN 10 DAYS B COMPLETE 1/3 OF WORK.
SO BEFORE LEAVING 2/3 OF WORK COMPLETED OR FOR 8(2/3 OF 12) DAYS THEY WERE TOGETHER.
SO TOTAL DAYS=10+8=18
Join the discussion

by abuc0112 » Thu Nov 29, 2012 1:50 pm
A = 1/20 & B = 1/30

Their Combined Rates are: 1/20 + 1/30 = 1/12

The work that is done by both A & B = 1/12*(t-10) = t-10/12

The work that is done by B alone = 1/30*10 = 1/3

The number of day it will take to complete the job is:

(t-10/12) + (1/3) = 1

= 18

OA= A
Join the discussion

by rajeshsinghgmat » Thu Mar 07, 2013 1:09 am
(B) 27 days
Join the discussion

by saurav.jha » Mon Mar 11, 2013 6:42 am
Rate of work by A in one day = 100/20= 5%
Rate of work by B in one day = 100/30= 3.33%
A quit 10 days before the completion means last 10 days B worked alone or he did 3.33 * 10 = 33.33%
Work done by A+B together = (100-33.33)=66.67%
So number of days A and B worked together= 66.67/8.33= 8 days
So total days 8+10 =18 days.
Join the discussion

by Java_85 » Sun Sep 29, 2013 8:46 am
18 days it is.
Join the discussion

by sanju09 » Fri Oct 04, 2013 1:55 am
This was a good question from some dubious source i don't remember ("dubious" because the answers are not in order and the persons are rechristened to be Alphabets already).

A GMAT look to it could have been as under:

Adam can complete a project in 20 days and Brian can complete the same project in 30 days. If they start working on the project together and Adam quits 10 days before the project is completed, in how many days will the project be completed?
(A) 12 days
(B) 16 days
(C) 18 days
(D) 26.67 days
(E) 27 days

What we already know is that their one day work is 1/12 of the total work.

I'd have preferred to plug back the numbers in to the question to check which one works. I'd have preferred to start from (C) for a reason i know.

So, if the project would have been completed in (C) 18 days then Adam must have quitted 8 days after they start, and in those 8 days the part of project done would have been 8/12 or 2/3, and the remaining 1/3 would have been completed by Brian alone in 10 days, which proves that Brian's rate on the project is 1/30 per day.

[spoiler]Hence (C) is correct.[/spoiler]
The mind is everything. What you think you become. -Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com
Join the discussion

by sahilbilga » Wed Feb 12, 2014 1:07 am
In 10 days, B will complete 1/3 of work. So before A quits, 2/3 of the work has to be completed. Therefore A and b together will do 1/12 of the work and they will do 2/3 of works in 8 days. Hence My answer is 18.
Join the discussion

by Scott@TargetTestPrep » Fri Dec 15, 2017 6:44 am
sanju09 wrote:A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?

A. 18 days
B. 27 days
C. 26.67 days
D. 16 days
E. 12 days
We are given that A can complete a project in 20 days and B can complete the same project in 30 days. Thus, the rate of A is 1/20 and the rate of B is 1/30. Since A quits 10 days before the project is completed, we can let t = the time in days worked by B, and thus, (t - 10) = the time in days worked by A. To determine t, we calculate the work done by A and the work done by B, using the work formula: work = rate x time.

work of A + work of B = 1

(1/20)(t - 10) + (1/30)(t) = 1

(t - 10)/20 + t/30 = 1

Multiplying the entire equation by 60, we have:

3t - 30 + 2t = 60

5t = 90

t = 18

Answer: A