A quits before the project is completed

This topic has expert replies
User avatar
Master | Next Rank: 500 Posts
Posts: 145
Joined: Tue Jan 31, 2012 6:50 am
Location: New Delhi
Thanked: 16 times
Followed by:2 members
GMAT Score:760

by nisagl750 » Sun Mar 25, 2012 6:40 am
If A quits 10 days before the job is completed, then B alone take 10 days to complete the remaining job.

B's 1 day's work = 1/30

So, B's 10 Days days' work = 10/30 = 1/3

That means, 2/3 of work was completed by A & B Together.

A&B together take = (20x30)/(20+30) Days to complete the full work = 12 Days

To complete 1 unit work A & B take 12 days...

So to complete 2/3 unit of work

A&B would take (2/3)x12 = 8 Days.

Total time to complete the work = (Time take by A&B together + 10 days) = 8+10

18 Days

Option A :)

User avatar
Master | Next Rank: 500 Posts
Posts: 308
Joined: Thu Mar 29, 2012 12:51 am
Thanked: 16 times
Followed by:3 members

by Lifetron » Mon Jul 30, 2012 4:25 am
(x-10)/20 + x/30 = 1

3x-30+2x=60

5x=90

x=18

User avatar
Senior | Next Rank: 100 Posts
Posts: 44
Joined: Sun Apr 01, 2012 4:07 am
Followed by:1 members

by chris558 » Sun Aug 26, 2012 7:19 am
Rate * Time = Distance
Let's first start by picking a number that represents 1 complete job. It would be easier if it were the LCD of 20 and 30... Let's say, 60.
So 1 job = 60

A: Rate * 20 = 60
Rate=3
B: Rate * 30 = 60
Rate = 2

They both work together to complete a job except B works the last 10 days by himself. The rate at which they both work together is 3 + 2.
Let t represent time (in days). Therefore the equation is:

5(t-10)+3(10)=60
5t-50+30=60
5t=80
t=18

Answer is A

Newbie | Next Rank: 10 Posts
Posts: 2
Joined: Thu Jun 21, 2012 11:07 am

by r_vgupta » Thu Aug 30, 2012 12:27 am
TOGETHER THEY CAN DO WORK IN 12 DAYS.
A LEFT 10 DAYS BEFORE.ie B WORKED ALONE FOR 10 DAYS.
IN 10 DAYS B COMPLETE 1/3 OF WORK.
SO BEFORE LEAVING 2/3 OF WORK COMPLETED OR FOR 8(2/3 OF 12) DAYS THEY WERE TOGETHER.
SO TOTAL DAYS=10+8=18

Junior | Next Rank: 30 Posts
Posts: 14
Joined: Fri Jun 18, 2010 8:52 am

by abuc0112 » Thu Nov 29, 2012 1:50 pm
A = 1/20 & B = 1/30

Their Combined Rates are: 1/20 + 1/30 = 1/12

The work that is done by both A & B = 1/12*(t-10) = t-10/12

The work that is done by B alone = 1/30*10 = 1/3

The number of day it will take to complete the job is:

(t-10/12) + (1/3) = 1

= 18

OA= A

Master | Next Rank: 500 Posts
Posts: 171
Joined: Tue Jan 08, 2013 7:24 am
Thanked: 1 times

by rajeshsinghgmat » Thu Mar 07, 2013 1:09 am
(B) 27 days

Newbie | Next Rank: 10 Posts
Posts: 7
Joined: Mon Mar 11, 2013 5:33 am

by saurav.jha » Mon Mar 11, 2013 6:42 am
Rate of work by A in one day = 100/20= 5%
Rate of work by B in one day = 100/30= 3.33%
A quit 10 days before the completion means last 10 days B worked alone or he did 3.33 * 10 = 33.33%
Work done by A+B together = (100-33.33)=66.67%
So number of days A and B worked together= 66.67/8.33= 8 days
So total days 8+10 =18 days.

User avatar
Master | Next Rank: 500 Posts
Posts: 234
Joined: Tue Jul 16, 2013 9:00 am
Location: West Virginia
Thanked: 9 times

by Java_85 » Sun Sep 29, 2013 8:46 am
18 days it is.

User avatar
GMAT Instructor
Posts: 3650
Joined: Wed Jan 21, 2009 4:27 am
Location: India
Thanked: 267 times
Followed by:80 members
GMAT Score:760

by sanju09 » Fri Oct 04, 2013 1:55 am
This was a good question from some dubious source i don't remember ("dubious" because the answers are not in order and the persons are rechristened to be Alphabets already).

A GMAT look to it could have been as under:

Adam can complete a project in 20 days and Brian can complete the same project in 30 days. If they start working on the project together and Adam quits 10 days before the project is completed, in how many days will the project be completed?
(A) 12 days
(B) 16 days
(C) 18 days
(D) 26.67 days
(E) 27 days

What we already know is that their one day work is 1/12 of the total work.

I'd have preferred to plug back the numbers in to the question to check which one works. I'd have preferred to start from (C) for a reason i know.

So, if the project would have been completed in (C) 18 days then Adam must have quitted 8 days after they start, and in those 8 days the part of project done would have been 8/12 or 2/3, and the remaining 1/3 would have been completed by Brian alone in 10 days, which proves that Brian's rate on the project is 1/30 per day.

[spoiler]Hence (C) is correct.[/spoiler]
The mind is everything. What you think you become. -Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com

Junior | Next Rank: 30 Posts
Posts: 26
Joined: Sat Apr 20, 2013 9:34 pm

by sahilbilga » Wed Feb 12, 2014 1:07 am
In 10 days, B will complete 1/3 of work. So before A quits, 2/3 of the work has to be completed. Therefore A and b together will do 1/12 of the work and they will do 2/3 of works in 8 days. Hence My answer is 18.

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 8086
Joined: Sat Apr 25, 2015 10:56 am
Location: Los Angeles, CA
Thanked: 43 times
Followed by:29 members

by Scott@TargetTestPrep » Fri Dec 15, 2017 6:44 am
sanju09 wrote:A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?

A. 18 days
B. 27 days
C. 26.67 days
D. 16 days
E. 12 days
We are given that A can complete a project in 20 days and B can complete the same project in 30 days. Thus, the rate of A is 1/20 and the rate of B is 1/30. Since A quits 10 days before the project is completed, we can let t = the time in days worked by B, and thus, (t - 10) = the time in days worked by A. To determine t, we calculate the work done by A and the work done by B, using the work formula: work = rate x time.

work of A + work of B = 1

(1/20)(t - 10) + (1/30)(t) = 1

(t - 10)/20 + t/30 = 1

Multiplying the entire equation by 60, we have:

3t - 30 + 2t = 60

5t = 90

t = 18

Answer: A

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage