It takes 7 high school kids, working at the same constant rates, 10 hours to paint a certain house. At what time will the house be complete if 7 kids start painting at 9am and one kid (assume identical rates for all kids) is added per hour starting 1 pm?

A. 3 pm
B. 4:30 pm
C. 5 pm
D. 5:20 pm
E. 6:20 pm

my answer is not D and here is what i did ... can you guys please help me where i made it wrong,ok?
7 kids paint a house in 10 hours so 1 kids will paint a house in 70 hours so 8 kids will paint a house in 70/8=8.75 hours
from 9 am till 1 pm is totally 4 hours and for 4 hours 7 kids painted 2/5 house so there would be 3/5 house left
so 8 kids will paint 3/5 house in =8.75*3/5=5.25 hours....
where did i do wrong?
Join the discussion
Source: — Problem Solving |

by winniethepooh » Sat Jul 16, 2011 9:01 pm
Hi,
You haven't really understood the question well..
At 1 PM and onwards after each hour there will be an addition of 1 kid after EACH hour.
so 7 kids take 70 hours, total work needed = 70 hrs.
at 1 PM = 28 hrs
at 2 pm= + 8 hrs
at 3 pm= + 9 hrs
at 4 pm= + 10hrs
at 5 pm= + 11hrs(At this point you reach 66 hrs, you need 4 hrs to complete 70 hrs and there are now 12 kids so 4/12)
at 5:20= + 4 hrs
Total= 70Hrs
Join the discussion

by mirantdon » Sun Jul 17, 2011 2:29 am
Good question +1 for D.
I did it the other way .
4/10 of the work is done by 1 pm
The remaining work = 0.6 .
So after 1 pm = (1/10 +1/70)[ work done by 7 of them plus the additional guy(1/70)]
2 pm = (1/10 +2/70)

Keep adding values till you reach 0.6 .. Use the options as well . they are pretty far apart .!
Join the discussion

by GMATGuruNY » Sun Jul 17, 2011 4:00 am
diebeatsthegmat wrote:It takes 7 high school kids, working at the same constant rates, 10 hours to paint a certain house. At what time will the house be complete if 7 kids start painting at 9am and one kid (assume identical rates for all kids) is added per hour starting 1 pm?

A. 3 pm
B. 4:30 pm
C. 5 pm
D. 5:20 pm
E. 6:20 pm

my answer is not D and here is what i did ... can you guys please help me where i made it wrong,ok?
7 kids paint a house in 10 hours so 1 kids will paint a house in 70 hours so 8 kids will paint a house in 70/8=8.75 hours
from 9 am till 1 pm is totally 4 hours and for 4 hours 7 kids painted 2/5 house so there would be 3/5 house left
so 8 kids will paint 3/5 house in =8.75*3/5=5.25 hours....
where did i do wrong?
Let rate per kid = 1 unit per hour.
Rate of 7 kids = 7 units per hour.
Work completed over 10 hours = r*t = 7*10 = 70 units.
Work completed by 7 kids from 9am to 1pm = 7*4 = 28 units.
Remaining work = 70-28 = 42 units.
Since each kid produces 1 unit per hour, as a kid is added each hour, the amount of work produced increases by 1 unit.
Over the next 4 hours, work produced = 8+9+10+11 = 38 units.
Time is now 1pm + 4 hours = 5pm.
Remaining work = 42-38 = 4 units.
Since only 4 more units need to be produced, the work is completed between 5pm and 6pm.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by goalevan » Sun Jul 17, 2011 7:11 am
Rate 7 kids = work/time = 1 house / 10 hours = 1/10 house/hour
Rate of 1 kid (each kid works at an equal rate) = 1/10 * 1/7 = 1/70 house/hour

For the first 4 hours, 9am - 12:59pm:
7 kids * 1/70 house/hour * 4 hours = 28/70 houses

New time: 1:00pm. Remaining work: 42/70 houses

For the next hours, 1:00-4:59pm:
8 kids * 1/70 house/hour * 1 hour = 8/70 houses
9 kids * 1/70 house/hour * 1 hour = 9/70 houses
10 kids * 1/70 house/hour * 1 hour = 10/70 houses
11 kids * 1/70 house/hour * 1 hour = 11/70 houses

New time: 4:00pm. Remaining work: 4/70 houses

12 kids * 1/70 house/hour * x hours = 4/70 houses
x = (4/70) / (12/70) = 4/12 = 1/3 hours.

Cumulative time is 4 + 1 + 1 + 1 + 1 + 1/3 hours or 8hrs:20min.

9:00am + 8hrs:20min = 5:20pm. D
Join the discussion

by diebeatsthegmat » Sun Jul 17, 2011 9:10 am
winniethepooh wrote:Hi,
You haven't really understood the question well..
At 1 PM and onwards after each hour there will be an addition of 1 kid after EACH hour.
so 7 kids take 70 hours, total work needed = 70 hrs.
at 1 PM = 28 hrs
at 2 pm= + 8 hrs
at 3 pm= + 9 hrs
at 4 pm= + 10hrs
at 5 pm= + 11hrs(At this point you reach 66 hrs, you need 4 hrs to complete 70 hrs and there are now 12 kids so 4/12)
at 5:20= + 4 hrs
Total= 70Hrs
ohh yeah i forgot reading the word "per hour". My bad!
Join the discussion

by amit2k9 » Mon Jul 18, 2011 10:05 pm
total man hours = 7*10 = 70

till 1 pm man hours = 7*4 = 28

till 5 pm man hours = 28 + 8 + 9 + 10 + 11 = 66

till 6 pm man hours = 66+12 = 78.

thus D is perfect.
For Understanding Sustainability,Green Businesses and Social Entrepreneurship visit -https://aamthoughts.blocked/
(Featured Best Green Site Worldwide-https://bloggers.com/green/popular/page2)
Join the discussion