right wrong
Pick an answer to see how members did
Log this miss in the free GMAT error log
Get the error logGet one like this every day: the free 60-day plan
Start the planA. 32
B. 100
C. 200
D. 240
E. 280
Answer: C
Source: e-GMAT
Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.
See classesLearn live with an expert or move at your own pace. Every option includes the complete TTP study system.
Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.
with Josh Braslow, 20+ years in test prep
Self-paced EA prep. Study on your schedule.
with
Complete access from day one. Study on your schedule.
right wrong
Pick an answer to see how members did
Log this miss in the free GMAT error log
Get the error logGet one like this every day: the free 60-day plan
Start the planSolution:M7MBA wrote: ↑Sun Dec 27, 2020 3:37 pmA group of 40 workers working together has to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only the 14th of the work was completed, then how many more workers should be recruited so that the work gets completed on time?
A. 32
B. 100
C. 200
D. 240
E. 280
Answer: C