Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

A contractor undertakes to dig a canal 12 km long...

Expert replies
by swerve » Thu Mar 01, 2018 5:17 am
A contractor undertakes to dig a canal 12 km long in 350 days and employs 45 men. After 200 days he finds that only 4.5 km of canal has bee completed. Find the number of extra men he must employ to finish the work in time?

A. 53
B. 55
C. 43
D. 59
E. 48

The OA is B.

Please, can any expert explain this PS question for me? I can't get the correct answer. I need your help. Thanks.
Join the discussion
Source: — Problem Solving |

by mbawisdom » Mon Mar 05, 2018 6:39 am
swerve wrote:A contractor undertakes to dig a canal 12 km long in 350 days and employs 45 men. After 200 days he finds that only 4.5 km of canal has bee completed. Find the number of extra men he must employ to finish the work in time?

A. 53
B. 55
C. 43
D. 59
E. 48

The OA is B.

Please, can any expert explain this PS question for me? I can't get the correct answer. I need your help. Thanks.
For the purpose of this question lets use M instead of KM

Lets' work out the rate/speed per day of a man:

Men * Rate * Days = Work
45 * Rate * 200 = 4500
Rate = 0.5m/day

We have 7500m (12000 - 4500) to dig.

Let's work out how many men this would take in 150 days:
Men * Rate * Days = Work
Men * 0.5 * 150 = 7500
Men = 100

Extra men needed = 100 - 45 = 55
Join the discussion

by Jeff@TargetTestPrep » Tue Mar 06, 2018 10:42 am
swerve wrote:A contractor undertakes to dig a canal 12 km long in 350 days and employs 45 men. After 200 days he finds that only 4.5 km of canal has bee completed. Find the number of extra men he must employ to finish the work in time?

A. 53
B. 55
C. 43
D. 59
E. 48
We can determine that the rate of the 45 men is 4.5/200 = 45/2,000 = 9/400.

We need to determine how many more men, working at the same constant rate must be used to dig another 7.5 km in 150 days. Thus, the entire crew needs to work at a rate of 7.5/150 = 75/1,500 = 1/20.

We can use a proportion to determine the total number of men needed to do the remainder of the job in the allotted time.

(x men)/(1/20) = (45 men)/(9/400)

9x/400 = 45/20

9x/400 = 9/4

9x/400 = 900/400

9x = 900

x = 100

Thus, the contractor needs to have a total crew of 100 men to complete the job on time. Since he already has 45 men, he needs to hire 100 - 45 = 55 more men.

Answer: B