Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

A company uses 2 machines to fill an order for 3,360 bottle

Expert replies
by BTGmoderatorDC » Thu Apr 04, 2019 6:53 pm
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

A company uses 2 machines to fill an order for 3,360 bottle caps. Machine A can produce 72 bottle caps every 24 minutes, and it can run for 4 hours before it must undergo a 3-hour recalibration procedure. Machine B can produce 48 bottle caps every 12 minutes, and it can run for 4 hours before it must undergo a 2-hour recalibration procedure. If both machines begin working at the same time, and are working whenever they are not being recalibrated, then how many of the 3,360 bottle caps are made by machine B ?

a. 1,440

b. 1,620

c. 1,680

d. 1,920

e. 2,160

OA D

Source: Princeton Review
Join the discussion
Source: — Problem Solving |

by Jay@ManhattanReview » Thu Apr 04, 2019 9:36 pm
BTGmoderatorDC wrote:A company uses 2 machines to fill an order for 3,360 bottle caps. Machine A can produce 72 bottle caps every 24 minutes, and it can run for 4 hours before it must undergo a 3-hour recalibration procedure. Machine B can produce 48 bottle caps every 12 minutes, and it can run for 4 hours before it must undergo a 2-hour recalibration procedure. If both machines begin working at the same time, and are working whenever they are not being recalibrated, then how many of the 3,360 bottle caps are made by machine B ?

a. 1,440

b. 1,620

c. 1,680

d. 1,920

e. 2,160

OA D

Source: Princeton Review
Given that Machine A can produce 72 bottle caps every 24 minutes, and it can run for 4 hours, it will produce 72/24 * 60 * 4 = 720 caps in 4 hours and that Machine B can produce 48 bottle caps every 12 minutes, and it can run for 4 hours, it will produce 48/12 * 60 * 4 = 960 caps in 4 hours.

Thus, in 4 hours, Machine A and B together will produce 720 + 960 = 1,680 caps. So, they would need 3360/1680 = 2 * 4 = 8 hours to produce 3,360 caps.

Thus, the number of caps out of the 3,360 bottle caps made by machine B = 2*960 = 1920

The correct answer: D

Hope this helps!

-Jay
_________________
Manhattan Review GRE Prep

Locations: Manhattan GMAT | Free LSAT Practice Questions | LSAT Prep Courses Manchester | SAT Prep Courses Hong Kong | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by Jay@ManhattanReview » Thu Apr 04, 2019 9:36 pm
BTGmoderatorDC wrote:A company uses 2 machines to fill an order for 3,360 bottle caps. Machine A can produce 72 bottle caps every 24 minutes, and it can run for 4 hours before it must undergo a 3-hour recalibration procedure. Machine B can produce 48 bottle caps every 12 minutes, and it can run for 4 hours before it must undergo a 2-hour recalibration procedure. If both machines begin working at the same time, and are working whenever they are not being recalibrated, then how many of the 3,360 bottle caps are made by machine B ?

a. 1,440

b. 1,620

c. 1,680

d. 1,920

e. 2,160

OA D

Source: Princeton Review
Given that Machine A can produce 72 bottle caps every 24 minutes, and it can run for 4 hours, it will produce 72/24 * 60 * 4 = 720 caps in 4 hours and that Machine B can produce 48 bottle caps every 12 minutes, and it can run for 4 hours, it will produce 48/12 * 60 * 4 = 960 caps in 4 hours.

Thus, in 4 hours, Machine A and B together will produce 720 + 960 = 1,680 caps. So, they would need 3360/1680 = 2 * 4 = 8 hours to produce 3,360 caps.

Thus, the number of caps out of the 3,360 bottle caps made by machine B = 2*960 = 1920

The correct answer: D

Hope this helps!

-Jay
_________________
Manhattan Review GRE Prep

Locations: Manhattan GMAT | Free LSAT Practice Questions | LSAT Prep Courses Manchester | SAT Prep Courses Hong Kong | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion