A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?
A) 4 2/3
B) 7
C) 9
D) 14
E) 24
Answer: D