Start the planA) 4 2/3
B) 7
C) 9
D) 14
E) 24
Answer: D
Source: GMAT Paper Tests
Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.
See classesLearn live with an expert or move at your own pace. Every option includes the complete TTP study system.
Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.
with Josh Braslow, 20+ years in test prep
Self-paced EA prep. Study on your schedule.
with
Complete access from day one. Study on your schedule.
right wrong
Pick an answer to see how members did
Log this miss in the free GMAT error log
Get the error logGet one like this every day: the free 60-day plan
Start the planA straightforward approach is to assign a nice value to the job.M7MBA wrote: ↑Tue Mar 23, 2021 7:55 amA carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?
A) 4 2/3
B) 7
C) 9
D) 14
E) 24
Answer: D
Source: GMAT Paper Tests