BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

A and B are two laborers who have been given the task to build a house. A can build a house in 20 days while B can build

Expert replies
by BTGmoderatorDC » Wed Feb 10, 2021 5:14 pm

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

A and B are two laborers who have been given the task to build a house. A can build a house in 20 days while B can build it in 30 days. But B went rogue and instead of building the house, he starts breaking it at the same rate. If A starts the work on the 1st day and they work alternately, in how many days will the house get built? (Assume once the house gets build, they will stop working)

A. 60 days

B. 115 days

C. 120 days

D. 140140 days

E. 121 1/3 days


OA B

Source: e-GMAT
Join the discussion
Source: — Problem Solving |

A can build a house in 20 days
B can build a house in 30 days

Work rate of A = 1/20
Work rate of B =1/30 days

So, in 2 days
$$\frac{1}{20}-\ \frac{1}{30}=\frac{3-2}{60}=\frac{1}{60}portion\ of\ the\ house\ will\ be\ \ built.$$

Assuming that they stopped working once the house is built, the last person to work will be A and B will not work on the last day.

No of days before the last day=>
$$\frac{60}{60}-\ \frac{1}{20}=\frac{60-3}{60}=\frac{57}{60}$$

if 2 days = 1/60 => $$\frac{114}{60}=\ \frac{x}{60}$$
$$x=114\ days$$

On the 15th day, A will only come to do 1/20 of the work to finish up so total no of days = 115 $$Answer\ is\ Option\ B$$
Join the discussion

BTGmoderatorDC wrote:
Wed Feb 10, 2021 5:14 pm
A and B are two laborers who have been given the task to build a house. A can build a house in 20 days while B can build it in 30 days. But B went rogue and instead of building the house, he starts breaking it at the same rate. If A starts the work on the 1st day and they work alternately, in how many days will the house get built? (Assume once the house gets build, they will stop working)

A. 60 days

B. 115 days

C. 120 days

D. 140140 days

E. 121 1/3 days


OA B


Source: e-GMAT
Solution:

We see that A’s rate is 1/20 and B’s rate is 1/30. Every two days, 1/20 - 1/30 = 3/60 - 2/60 = 1/60 of the house is built (notice we are subtracting 1/30 from 1/20 because B is breaking the house instead of building the house).

Since 1/60 of the house is built every two days, one might think that it will then take 2 x 20 = 120 days to build the entire house. However, remember that, once the house gets finished by A, then work will stop, and B will not have an opportunity to break it on the following day. Therefore, it will take some number less than 120 days to build the house, so 115 should be the correct answer. But let’s verify it.

Since 114/2 = 57, after 114 days, 1/60 x 57 = 57/60 = 19/20 of the house will be built and on the following day, the 115th day, 1/20 more of the house will be built by A. Therefore, by the end of the 115th day, 19/20 + 1/20 = 1 entire house will be built.

Answer: B