BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

2 men do?

Expert replies
by sanju09 » Thu Jan 28, 2010 12:43 am
15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men do?
(A) 18
(B) 20
(C) 25
(D) 27
(E) 30
The mind is everything. What you think you become. -Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com
Join the discussion
Source: — Problem Solving |

by ajith » Thu Jan 28, 2010 12:50 am
sanju09 wrote:15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men do?
(A) 18
(B) 20
(C) 25
(D) 27
(E) 30
Total work = 15*21*8 men hours

= 3/2*15*21*8 women hours

Now with 6 hours and 21 women no of days = 2*15*21*4/6*21 = 20 Days
Always borrow money from a pessimist, he doesn't expect to be paid back.
Join the discussion

by kvamsy » Thu Jan 28, 2010 2:13 am
ajith wrote:
sanju09 wrote:15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men do?
(A) 18
(B) 20
(C) 25
(D) 27
(E) 30
Total work = 15*21*8 men hours

= 3/2*15*21*8 women hours

Now with 6 hours and 21 women no of days = 2*15*21*4/6*21 = 20 Days

I believe answer is E , Can I have OA please
Join the discussion

by thephoenix » Thu Jan 28, 2010 2:21 am
3w=2m----->21w=14m

15*8*21(man hours)=14*6*n(man hours;21 women=14 men)

solving n=30 days

hence E
Oa pls
Join the discussion

by sanju09 » Thu Jan 28, 2010 2:30 am
OA is [spoiler]E[/spoiler]
The mind is everything. What you think you become. -Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com
Join the discussion

by ajith » Thu Jan 28, 2010 3:04 am
ajith wrote:
sanju09 wrote:15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men do?
(A) 18
(B) 20
(C) 25
(D) 27
(E) 30
Total work = 15*21*8 men hours

= 3/2*15*21*8 women hours

Now with 6 hours and 21 women no of days = 2*15*21*4/6*21 = 20 Days
Now with 6 hours and 21 women no of days = 3*15*21*4/6*21 = 30 Days

Slight calculation mistake :( it is indeed 30 days
Always borrow money from a pessimist, he doesn't expect to be paid back.