20 men can finish a piece of work in 30 days.When should 5 men leave the work so that it may be finished in 35 days?
a. 10 days
b. 20 days
c. 25days
d. 15 days
a. 10 days
b. 20 days
c. 25days
d. 15 days
BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course
RedeemTarget Test Prep · GMAT
Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.
TTP has worked incredibly hard to build the best test prep experience possible, and winning Newsweek’s 2026 Readers’ Choice Award for Best Test Prep would mean a lot to them. If TTP has helped you, they’d be incredibly grateful for your vote. You can vote once each day through September 9.

with Chris Peckover

with Logan Thompson
Complete access from day one. Study on your schedule.
Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.
Let rate per man = 1 unit per day.neya wrote:20 men can finish a piece of work in 30 days.When should 5 men leave the work so that it may be finished in 35 days?
a. 10 days
b. 20 days
c. 25days
d. 15 days
We are given that 20 workers can complete a job in 30 days. Since rate = work/time, the rate of the 20 workers is 1/30. We can let x be the number of days it would take 5 fewer workers (i.e., 15 workers) to complete the job (from beginning to end); thus the rate of the 15 workers would be 1/x. Let's determine x using the following proportion:neya wrote:20 men can finish a piece of work in 30 days.When should 5 men leave the work so that it may be finished in 35 days?
a. 10 days
b. 20 days
c. 25days
d. 15 days



let one man can break one stone in a dayneya wrote:20 men can finish a piece of work in 30 days.When should 5 men leave the work so that it may be finished in 35 days?
a. 10 days
b. 20 days
c. 25days
d. 15 days
New here Create free account