Working at their individual same constant rate, 24 machines

This topic has expert replies
Moderator
Posts: 2209
Joined: Sun Oct 15, 2017 1:50 pm
Followed by:6 members

Timer

00:00

Your Answer

A

B

C

D

E

Global Stats

Source: e-GMAT

Working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. On a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. Compared to normal days, what is the extra time taken to complete the production job on that day?

A. 20 minutes
B. 30 minutes
C. 40 minutes
D. 1 hour
E. 1 hour 20 minutes

The OA is C

GMAT/MBA Expert

User avatar
Elite Legendary Member
Posts: 10392
Joined: Sun Jun 23, 2013 6:38 pm
Location: Palo Alto, CA
Thanked: 2867 times
Followed by:511 members
GMAT Score:800

by [email protected] » Fri Feb 15, 2019 11:28 am
Hi All,

We're told that while working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. However, on a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. We're asked - relative to 'normal' days - what is the EXTRA time taken to complete the production job on that day.

This is an example of a "Work" questions - and it often helps to first determine the total amount of work needed to complete the job. With 24 machines that each work 10 hours at the same rate, the total amount of work needed to complete a job is (24)(10) = 240 machine-hours of work.

Thus, if we had just 1 machine, then it would need to work 240 hours. If we had 2 machines, they would each need to work 120 hours, etc.

We're told that 8 of the machines do NOT work for the first 2 hours, meaning that the remaining 24 - 8 = 16 machines DO work for those first 2 hours....

(16)(2) = 32 machine-hours of work completed. This leaves 240 - 32 = 208 hours of machine work left to complete.

When all 24 machines are working, 24 machine-hours of work are completed each hour....
208/24 = 8 16/24 hours = 8 2/3 hours of time are then needed to complete the job.
Total time = 2 hours + 8 2/3 hours = 10 2/3 hours.... so the extra 2/3 hours = (2/3)(60 minutes) = 40 minutes extra

Final Answer: C

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 7247
Joined: Sat Apr 25, 2015 10:56 am
Location: Los Angeles, CA
Thanked: 43 times
Followed by:29 members

hi

by Scott@TargetTestPrep » Mon Feb 18, 2019 5:57 pm
BTGmoderatorLU wrote:Source: e-GMAT

Working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. On a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. Compared to normal days, what is the extra time taken to complete the production job on that day?

A. 20 minutes
B. 30 minutes
C. 40 minutes
D. 1 hour
E. 1 hour 20 minutes

The OA is C
The rate of 24 machines is 1/10.

On a certain day 16 machines first ran for 2 hours.

The rate of the 16 machines is:

16/n = 24/(1/10)

16/n = 240

16 = 240n

n = 16/240 = 1/15

Thus, when 16 machines work for 2 hours, the fraction of the job completed is 1/15 x 2 = 2/15.

Thus, 13/15 of the job needs to be completed by 24 machines. The time it will take to complete the job is:

(13/15)/(1/10) = 130/15 = 26/3 hours

Therefore, the total time spent on the job is 2 + 26/3 = 32/3 hours = 10 2/3 hours = 10 hours 40 minutes, which is 40 minutes more than on a normal day.

Alternate Solution:

Since the 24 machines normally require 10 hours to get the job done, the total time required is 240 machine hours.

On the day of the malfunction, only 16 machines were working for the first 2 hours; thus, they accomplished 16 x 2 = 32 machine hours of production.

When all 24 machines were back in production, we see that there were 24 machines that needed to accomplish the remaining (240 - 32) = 208 machine hours of production. This results in 208/24 = 8 2/3 additional hours.

Thus, on the day of the malfunction, the machines had to work for 2 + 8 2/3 = 10 2/3 hours, which is 40 minutes longer than normal.

Answer: C

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage