BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work rates - fraction of a job

Expert replies
by AleksandrM » Mon Jun 30, 2008 5:03 pm
The following problem appeared on my MGMAT CAT. MGMAT only uses the plugging in method for this problem. However, I would like to see an algebraic solution.

Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of the job that B will not have to complete because of A's help?

A) x - y/x + y
B) x/y - x
C) x + y/xy
D) y/x - y
E) y/x + y
Join the discussion
Source: — Problem Solving |

by jay2007 » Mon Jun 30, 2008 8:07 pm
If both A and B work together they can complete the job in xy/(x+y) hours.

In "y" hours B completes "1" job
Therefore in xy/(x+y) hours B completes x/(x+y) job.

So the remaining portion of the job is: 1-x/(x+y) which is y/(x+y).

So, the answer is E.

Could you please post the OA?
Join the discussion

by AleksandrM » Tue Jul 01, 2008 9:30 am
Answer is E.

Can you please elaborate. I would like to see the setup and the actual steps. Thanks.
Join the discussion

by szapiszapo » Tue Jul 01, 2008 11:56 am
A does the job in x hours, meaning that his rate is rA = 1 / x
B does the job in y hours, meaning that his rate is rB = 1 / y

In z hours (the time needed to complete the job), A will have performed z / x of the job and B will have performed z / y of the job

therefore z/x + z/y = 1 job, i.e. z = xy / (x+y)

Given that B needs y hours to complete the job, the number of hours that B will not have to work (thanks to A) is (y - z) which, multiplied by his rate, give us a fraction F = (y - z) / y = 1 - (z/y)

F = 1 - (x/(x+y))
thus
F = y / (x + y)

Answer E


hope it helps