BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work rate problem

Problem Solving — algebra and arithmetic (GMAT Focus Edition)
Expert replies
by ysfpsu » Mon Mar 14, 2011 5:41 pm
Okay I feel stupid posting this question because it seems really easy but I, for the life of me, can't figure it out...(doesn't bode well for my Quant section..)

One pump drains one-half of a pond in 3 hours, and then a second pump starts draining the pond. The two pumps working together finish emptying the pond in one-half hour. How long would it take the second pump to drain the pond if it had to do the job alone?

Answer is: 1.2 hours

I know you have to find the rate of pump A (1/6), find the rate of Pump A and B together ( 1hr). Subtract to get rate of Pump B then using W = rt, find the time. But I can't get the answer!! Please help!
Join the discussion
Source: — Quantitative Reasoning |

by Geva@EconomistGMAT » Mon Mar 14, 2011 11:50 pm
ysfpsu wrote:Okay I feel stupid posting this question because it seems really easy but I, for the life of me, can't figure it out...(doesn't bode well for my Quant section..)

One pump drains one-half of a pond in 3 hours, and then a second pump starts draining the pond. The two pumps working together finish emptying the pond in one-half hour. How long would it take the second pump to drain the pond if it had to do the job alone?

Answer is: 1.2 hours

I know you have to find the rate of pump A (1/6), find the rate of Pump A and B together ( 1hr). Subtract to get rate of Pump B then using W = rt, find the time. But I can't get the answer!! Please help!
deal with this sort of problem by plugging in a comfortable number for the work. You want a number that is easily divisible by 2 (one half of a pond), and by three (3 hours) so that you avoid fractions. So assume that the pond is 6 liters.

The first pump drains one half of the pond (3 liters) in 3 hours, or a rate of 1 liter an hour.
The second pump kicks in, and the two pumps together drain the pool (the remaining 3 liters) in half an hour: meaning that they work at a rate of 3/1/2 = 3*2 = 6 liters an hour together.

since the combined rate is 6 li/h but the first pump's rate is 1 liter/hr, the second pump's rate is the remaining 5 liters an hour. If the pump had to drain the entire pool (6 liters) at 5 lt/hr, it would take it 6/5 = 1.2 hours to do so.
Geva
Senior Instructor
Master GMAT
1-888-780-GMAT
https://www.mastergmat.com
Join the discussion

by gmatscottsdale » Mon Mar 21, 2011 2:30 am
Another way to approach this problem would be:

We know time taken by Machine A and Machine B to work together and finish the job is:

T = AB/(A + B)

In this case, the first pump finished draining half the pond in 3 hrs. To finish draining the full pond, it would take 6 hrs.

Similarly, when both machines started working together to rest the second half of the pond, they finished the job in 0.5 hrs. If they started working together right from the beginning, they would have drained the entire pond in 1 hr.

(I basically made sure I calculate the number of hours to drain the entire pond since the answer is asking how long will it take to drain the entire pond by using the second pump independently).


We plug our values, A = 6, B = unknown (x), and T = 1

6*x/(6 + x) = 1

=> 6x = (6 + x)

=> 6x - x = 6

=> 5x = 6

x = 6/5 = 1.2 hrs

:)
Join the discussion

by gmatscottsdale » Mon Mar 21, 2011 2:33 am
In reference to the point where you got stuck on this particular problem:

You are not getting the correct answer in the pump problem because you are probably forgetting to flip your answer.

You are right, you subtract:

Rate B = Rate(Combined) - RateA = 1 - 1/6 = 5/6

However, remember that Rate B = Work done/time, We know Work done is 1 and time = x

5/6 = 1/x => x = 6/5 = 1.2 hrs :)