BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Math question .. need help

Expert replies
by richlittl » Thu Oct 16, 2008 9:34 am
Two machines are sawing wood but due to space limitations only one at a time can operate. Machine A is used for the first shift and the other machine for the second shift, while both work half of the third shift. Machine A can do the job in 12 days if it worked two shifts and Machine B can do the job in 15 days if it worked two shifts. How many days will it take to do the job with current work schedule?

A.14

B.13

C.11

D.9

E.7

Isn't a "shift" a defined time frame??
Join the discussion
Source: — Problem Solving |

by mental » Thu Oct 16, 2008 10:29 am
Total 3 shifts worked per day, with each machine working for 1.5 shifts

Machine A:
2 shifts a day...................12 days to complete the work
1.5 shifts/day...................12*2/1.5 = 16 days to complete the work
in one day it does 1/16 of work

Machine B:
2 shifts a day...................15 days to complete the work
1.5 shifts/day...................15*2/1.5 = 20 days to complete the work
in one day it does 1/20 of work

working together they do 1/16 + 1/20 = 9/80 of work in a day
they complete the work in 80/9 = 9 approx

IMO: D
Join the discussion

by stop@800 » Thu Oct 16, 2008 10:01 pm
I am also getting 80/9
but I think there is no approximate in question so we must be missing something
Join the discussion

by mental » Thu Oct 16, 2008 11:54 pm
OA please
Join the discussion

by richlittl » Fri Oct 17, 2008 12:53 pm
D. 9 days
Join the discussion