BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work problem

Expert replies
by prince11 » Wed May 20, 2009 9:05 am
Hi,

Can anyone please explain the work problem below? I get confuse when work done is more than 1. Is there a website that has these kinds of problems? Many websites have problems involving 1 work done. Thanks in advance.


Two carpenters, working in the same pace, can build 2 desks in two hours and a half. How many desks can 4 carpenters build in 4 hours?

(a) 2.4
(b) 3.6
(c) 4.2
(d) 5.5
(e) 6.4

[spoiler]The best answer is E.
2 carpenters build 2 desks in 2.5 hours ---> 4 carpenters build 4 desks in 2.5 hours ----> In 4 hours there are (4/2.5 = 1.6) time units. And (4 x 1.6) is 6.4 desks.[/spoiler]
Join the discussion
Source: — Problem Solving |

Re: Work problem

by dtweah » Wed May 20, 2009 9:18 am
prince11 wrote:Hi,

Can anyone please explain the work problem below? I get confuse when work done is more than 1. Is there a website that has these kinds of problems? Many websites have problems involving 1 work done. Thanks in advance.


Two carpenters, working in the same pace, can build 2 desks in two hours and a half. How many desks can 4 carpenters build in 4 hours?

(a) 2.4
(b) 3.6
(c) 4.2
(d) 5.5
(e) 6.4

[spoiler]The best answer is E.
2 carpenters build 2 desks in 2.5 hours ---> 4 carpenters build 4 desks in 2.5 hours ----> In 4 hours there are (4/2.5 = 1.6) time units. And (4 x 1.6) is 6.4 desks.[/spoiler]
This site should give you a good primer on work rate problems of different kinds. After reviewing it you should be able to handle this. Give it a try.

https://www.purplemath.com/modules/workprob.htm
Join the discussion

by ssmiles08 » Wed May 20, 2009 10:04 am
I learnt how to do these types of problems based on someone else's post so this method might help you as well.

The trick is to hold 1 variable constant temporarily.

c d h
2 2 5/2 (2.5)

I will choose to hold (hours) constant. and I will divide the rest by 2

so 1 carpenter will be able to do 1 desk in 2.5 hours

c d h
1 1 5/2

Now I want to get the hours to 1, so i will hold the (carpenter) constant, and I will divide desks and hours by 5/2

so now I have 1 carpenter can do 2/5 desks in 1 hour.

c d h
1 2/5 1

I want 4 carpenters so I hold (hours) constant again and multiply carpenters and desks by 4

c d h
4 8/5 1

Lastly I want 4 hours so I hold (carpenters) constant and multiply hours and desks by 4

c d h
4 32/5 4

32/5 = 6.4 desks


I know this is a long explanation but I broke it down step by step so hopefully you can understand this better.
Join the discussion

by raleigh » Wed May 20, 2009 10:48 am
Set up a ratio.

Treat the 2 carpenters as one unit. 1 unit can build 2 desks/2.5 hours. This is the same as (2/2.5)(desks/hour). That fraction looks hideous, so change 2.5 to a fraction and simplify. So we get 1 unit can build (4/5)(desks/hour).

Then 2 units (4 carpenters) will double the rate they build, 2*(4/5)(desks/hour) = (8/5)(desks/hour)

Now set up an equation using these ratios:

(8/5)(desks/hour) = (x/4) (desks/hour)

5x = 32
x = 6.4