BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work problem

Expert replies
by crackgmat007 » Wed May 06, 2009 9:38 am
Q: Working alone at its constant rate, machine K took 3 hours to produce 1/4of the units produced
last Friday. Then machine M started working and the two machines, working simultaneously at
their respective constant rates, took 6 hours to produce the rest of the units produced last Friday.
How many hours would it have taken machine M, working alone at its constant rate, to produce all
of the units produced last Friday?
A. 8
B. 12
C. 16
D. 24
E. 30

OA – D

Total hours of work is 12 (1/4 is 3 hours, hence 1 is 12 hours). Balance work is 9 hours, which is completed by M & K in 6 hours. Can someone explain how do I go from here?
Join the discussion
Source: — Problem Solving |

by DanaJ » Wed May 06, 2009 10:12 am
You're almost there.

Since it took machine K 3 hours to complete 1/4 of the job, it would indeed take it 12 hours to do it alone.
Since it took both machines 6 hours to complete the remaining 3/4 of the job, it would take them both 4/3 * 6 = 8 hours to complete the whole thing.

Now all you need to do is apply that "work formula"

1/k + 1/m = 1/(mk) - where k = time it takes k to complete the job alone; m = time it takes m to complete the job alone; mk = time it takes both machines to do the job working together.

1/12 + 1/m = 1/8

1/m = 1/8 - 1/12 = 1/24 ------------ m = 24.
Join the discussion

by crackgmat007 » Wed May 06, 2009 11:10 am
got it...thanks much
Join the discussion

by Bhattu » Fri May 08, 2009 4:20 am
I went a bit more basic on this.

K took 3 hrs to do 1/4 of the job, then K took 6 hrs to do 1/2 the job. Therefore K did 3/4 of the work in 9 Hrs and M did 1/4 of the work in 6 hrs.

If M did 1/4 in 6hrs, it would take M 6*4 hours to complete the job.

I would go for the earlier solution as it sticks to the tried and tested formula for work problems