BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work Problem

Problem Solving — algebra and arithmetic (GMAT Focus Edition)
Expert replies
by talaangoshtari » Mon Apr 04, 2016 4:13 am
The constant rate at which machines A works is 3/4 of the constant rate at which machine B works. Under normal conditions, machine A would complete x lots in 2 days. However, when a technician attempts to use machines A and B simultaneously, there is not enough electrical power to run both machines at full power. As a result, running the machines simultaneously reduces the work rate of each machine by 20%.

How long will it take the machines to complete 3x lots, working simultaneously?
Join the discussion
Source: — Quantitative Reasoning |

by MartyMurray » Mon Apr 04, 2016 5:02 am
One great, pretty much fail safe way to handle work problems is to start by finding the rates of each machine or person doing the work.

A Normal Rate: x/2 per day

B Normal Rate: (x/2)/(3/4) = 2x/3 per day

Rate Together: A Rate + B Rate = 3x/6 + 4x/6 = 7x/6 Per Day

Together Running At Reduced Rate: 7x/6 x 4/5 = 28x/30 = 14x/15

3x/(14x/15) = 3/(14/15) = 45/14 Days Working Simultaneously
Last edited by MartyMurray on Tue Apr 05, 2016 11:35 am, edited 1 time in total.
Marty Murray
Perfect Scoring Tutor With Over a Decade of Experience
MartyMurrayCoaching.com
Contact me at [email protected] for a free consultation.
Join the discussion

by [email protected] » Mon Apr 04, 2016 9:06 am
Hi talaangoshtari,

When posting GMAT questions, you should make sure to post the 5 answer choices as well. In many cases, the answers provide 'clues' as to how you can approach the question. Without having that option, we're essentially forced to 'do math' (as Marty has shown), although you could also TEST VALUES (choose a value for X and then calculate from there).

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by talaangoshtari » Mon Apr 04, 2016 11:01 am
Hi.
I know that. But, this is a GRE question. In GRE we have some questions without the answer choices.
Join the discussion

by regor60 » Tue Apr 05, 2016 10:55 am
Marty Murray wrote:One great, pretty much fail safe way to handle work problems is to start by finding the rates of each machine or person doing the work.

A Normal Rate: x/2 per day

B Normal Rate: (x/2)/(3/4) = 2x/3 per day

Rate Together: A Rate + B Rate = 3x/6 + 4x/6 = 7x/6 Per Day

Together Running At Reduced Rate: 7x/6 x 3x/4 = 21x/24 = 7x/8

3x/(7x/8) = 3/(7/8) = 24/7 Days Working Simultaneously

Question indicates 20% reduction not 25%. Would think T is 45/14
Join the discussion

by MartyMurray » Tue Apr 05, 2016 11:32 am
regor60 wrote:Question indicates 20% reduction not 25%. Would think T is 45/14
Yup. Fixed.
Marty Murray
Perfect Scoring Tutor With Over a Decade of Experience
MartyMurrayCoaching.com
Contact me at [email protected] for a free consultation.
Join the discussion

by Matt@VeritasPrep » Fri Apr 15, 2016 1:40 pm
Another popular approach is picking a value. Suppose x = 60. Then

A does 30 lots a day
B does 40 lots a day

after the power reduction,

A does 24 lots a day
B does 32 lots a day

So we've got 56 lots a day with the two together, and 180 lots for them to do.

180/56 => 4*45 / 4*15 => 45/14